Robinson Nuclear Plant - License Renewal Application
Renewed License Issued 04/19/2004
On this page
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
License Renewal Review Schedule*
* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal Application |
06/17/02 |
06/17/02 |
FRN Published for Receipt & Acceptability |
07/18/02 |
02/12/02 |
FRN Published for Acceptance/Rejection/ Opportunity for Hearing of LRA |
08/19/02 |
08/16/02 |
FRN Published for Intent/Environmental Scoping Mtg |
08/25/02 |
08/22/02 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
09/19/02 |
09/19/02 |
Scoping and Screening Methodology Audit Complete |
09/20/02 |
09/20/02 |
Environmental Scoping Meeting |
09/25/02 |
09/25/02 |
Environmental Scoping Period Ends |
10/25/02 |
10/25/02 |
Environmental RAIs Issued |
12/02/02 |
10/23/02 |
Environmental RAI Responses Received |
01/20/03 |
01/20/03 |
Safety RAIs Issued |
02/11/03 |
02/11/03 |
Scoping Inspection Complete |
04/04/03 |
04/04/03 |
Safety RAI Responses Received |
04/28/03 |
04/28/03 |
Draft Supplemental Environmental Impact Statement Issued |
05/16/03 |
05/05/03 |
FRN Published for Availability/Comment on Draft SEIS |
05/16/03 |
05/14/03 |
Public Mtg to Discus Draft SEIS |
06/25/03 |
06/25/03 |
End of Draft SEIS Comment Period |
07/30/03 |
07/30/03
|
Aging Management Review Inspection Complete |
07/03 |
06/27/03 |
SER with Open Items Issued |
08/25/03 |
08/25/03 |
Optional Final Inspection Complete |
09/10/03 |
09/10/03 |
ACRS Subcommittee Mtg on SER with Open Items |
09/30/03 |
09/30/03 |
SER Open Item Responses Received |
11/07/03 |
11/07/03 |
Final SEIS Issued |
12/31/03 |
12/12/03 |
FRN Published for Availability of Final SEIS |
01/02/04
|
12/15/03
|
SER Issued |
01/21/04 |
01/20/04 |
Regional Administrator's Letter Issued |
02/03/04 |
12/17/03 |
ACRS Full Committee Mtg on SER |
03/04/04 |
03/04/04 |
ACRS Letter Issued |
03/04 |
03/18/04 |
Staff Recommendations to Director, NRR |
04/12/04 |
04/09/04 |
Decision - Director, NRR (license issued) |
04/19/04 |
04/19/04 |
Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Supplement 13, Regarding H.B. Robinson Steam Electric Plant, Unit No. 2, was published December 2003
This supplement documents the NRC staff's review of the environmental issues at Robinson, Unit 2 in support of Carolina Power and Light Company's (CP&L) application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.
Safety Evaluation Report
The NRC staff reviewed the Robinson license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was first issued in August 2003, as "Safety Evaluation Report with Open Items Related to the License Renewal of H.B. Robinson, Unit 2". The report is available in ADAMS under accession number ML032370382.
In March 2004, the report "Safety Evaluation Report - Related to the License Renewal of the H. B. Robinson Steam Electric Plant, Unit 2," was issued as NUREG-1785. The report is also available in ADAMS under accession number ML040200981.
Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Date |
Description |
03/04/2004 |
Meeting with Carolina Power & Light to discuss issues related to the Safety Evaluation Report (SER) for the Robinson Nuclear Plant, License Renewal Application
|
09/30/2003 |
Meeting with Carolina Power & Light to discuss issues related to the Safety Evaluation Report (SER) with open items for the Robinson Nuclear Plant, License Renewal Application
|
06/27/2003 |
Meeting with Carolina Power & Light to present the results of the NRC's second regional inspection (Aging Management Review) of the company's license renewal program at Robinso
|
06/25/2003 |
Meeting with Carolina Power & Light to discuss the Draft Environmental Impact Statement (EIS) for the Robinson Nuclear Plant License Renewal Applicatio
|
05/20/2003 05/21/2003 |
Meeting with Carolina Power & Light to discuss and clarify the final requests for additional information (RAI) response
|
04/04/2003 |
Meeting with Carolina Power & Light to present the results of the NRC's first regional inspection (Scoping and Screening) of the company's license renewal program at Robinson
|
01/08/2003 01/09/2003 |
Meeting with Carolina Power & Light to discuss draft request for additional information (RAI) for the Robinson Nuclear Plant License Renewal Application
|
12/17/2002 12/18/2002 12/19/2002 |
Meeting with the Carolina Power & Light to discuss draft requests for addition information for the Safety Evaluation Report of the Robinson Nuclear Plant License Renewal Application
|
10/23/2002 10/24/2002 |
Meeting with the Carolina Power & Light to discuss the review tools provided by the applicant for the Robinson Nuclear Plant License Renewal Application
|
10/23/2002 |
Meeting with the Carolina Power & Light to discuss the electrical area of the Robinson Nuclear Plant License Renewal Application
|
09/25/2002 |
Meeting to discuss the Environmental Scoping Process for the Robinson Nuclear Plant License Renewal Application
|
09/20/2002 |
Meeting with the Carolina Power & Light to discuss the results of the NRC's initial inspection (Scoping Methodology) of the Company's license renewal program at Robinson Nuclear Plant
|
07/18/2002 |
Meeting with the Carolina Power & Light to provide the Nuclear Regulatory Commission (NRC) staff with an overview of the Robinson Nuclear Plant License Renewal Application
|