Comanche Peak Nuclear Power Plant Units 1 and 2 – License Renewal Application

On this page:
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Note: The Comanche Peak license renewal application is contained in ADAMS Package ML22276A082.

License Renewal Review Schedule
These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal Application (LRA) |
10/2022 |
10/03/2022 |
Publish Federal Register Notice (FRN) – LRA Availability |
10/2022 |
10/31/2022 |
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing |
11/2022 |
11/29/2022 |
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping |
11/2022 |
12/13/2022 |
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping |
01/2023 |
01/17/2023 |
Environmental Scoping Period Ends |
01/2023 |
03/13/2023 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
01/2023 |
01/30/2023 |
Issue Draft Supplemental Environmental Impact Statement (SEIS) |
09/2023 |
|
Public Meeting – Draft SEIS Meeting, If Needed |
10/2023 |
|
End of DSEIS Comment Period |
11/2023 |
|
Issue Safety Evaluation Report (SER) |
12/2023 |
|
ACRS Subcommittee Meeting |
02/2024 |
|
Issue Final SEIS |
03/2024 |
|
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS |
04/2024 |
|
ACRS Full Committee Meeting |
06/2024 |
|
Decision – Director, NRR |
09/2024 |
|

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Date |
Description |
01/10/2023 |
Meeting to discuss the license renewal process and environmental scoping for Comanche Peak Nuclear Power Plant, Units 1 and 2
|
01/17/2023 |
Meeting to discuss the license renewal process and environmental scoping for Comanche Peak Nuclear Power Plant, Units 1 and 2
|
02/23/2023 |
Meeting to discuss the license renewal process and environmental scoping for Comanche Peak Nuclear Power Plant, Units 1 and 2 (additional scoping meeting)
|

Project Managers for Comanche Peak, Units 1 & 2
Comanche Peak, Units 1 & 2 PMs |
License Renewal (Safety) |
Mark Yoo |
License Renewal (Environmental) |
Tam Tran |
Lead Power Plant |
Dennis Galvin |

Page Last Reviewed/Updated Tuesday, June 20, 2023