Callaway Plant, Unit 1 – License Renewal Application
Renewed License Issued on 03/06/2015
On this page:
Application Information:
License Renewal Review Schedule
Milestones |
Schedule Date |
Actual Date |
Receive license renewal application (LRA) |
12/19/11 |
12/19/11 |
Publish Federal Register Notice (FRN) – LRA availability |
01/2012 |
01/03/12 |
Publish FRN – acceptance/rejection and opportunity for hearing |
02/2012 |
02/24/12 |
Publish FRN – environmental scoping meeting |
02/2012 |
02/24/12 |
Public Meeting – License Renewal Overview and Environmental Scoping meeting |
03/14/12 |
03/14/12 |
Deadline for filing hearing requests and petitions for intervention |
04/24/12 |
04/24/12 |
Environmental scoping period ends |
04/24/12 |
04/24/12 |
Audit – Scoping & Screening Audit Methodology |
04/16/12 |
04/16/12 |
Audit – Aging Management Programs |
04/30/12 |
04/30/12 |
Audit – Environmental |
05/22/12 |
05/22/12 |
Issue safety evaluation report (SER) with open items |
04/2013 |
04/23/13 |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting |
05/2014 |
05/22/14 |
Issue draft supplemental environmental impact statement (SEIS) |
02/2014 |
02/12/14 |
Publish FRN – draft SEIS available for comments |
02/2014 |
02/21/14 |
Public Meeting – draft SEIS meeting |
03/2014 |
03/19/14 |
End of draft SEIS comment period |
04/2014 |
04/07/14 |
Issue final SER |
09/2014 |
08/21/14 |
ACRS full committee meeting |
10/2014 |
10/02/14 |
Issue final SEIS |
11/2014 |
10/29/14 |
U.S. Environmental Protection Agency FRN Published – availability of final SEIS |
11/2014 |
11/14/14 |
Decision – Director, Office of Nuclear Reactor Regulation |
03/2015 |
03/06/15 |
Safety Evaluation Report
The NRC staff reviewed the Callaway Plant, Unit 1, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued on April 23, 2013, as "Safety Evaluation Report with Open Items Related to the License Renewal of Callaway Plant, Unit 1."
Subsequently, on August 21, 2014, the document "Safety Evaluation Report Related to the License Renewal of Callaway Plant, Unit 1" was issued. In March 2015, the staff published the final "Safety Evaluation Report Related to the License Renewal of Callaway Plant, Unit 1" as NUREG-2172.
Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Callaway Plant, Unit 1 (NUREG-1437, Supplement 51) Final Report," was published in October 2014. This supplement documents the NRC staff's review of the environmental issues at Callaway Plant, Unit 1 regarding the Ameren application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC staff's recommendation regarding the proposed action.
Public Involvement
The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date |
Description |
03/19/2014 |
Meeting to discuss the preliminary results of the environmental review for Callaway Plant.
|
03/14/2012 |
Meeting to discuss the license renewal process and environmental scoping for Callaway Plant.
|