Dresden Nuclear Power Station, Units 2 and 3 – Subsequent License Renewal Application

On this page:

Dresden Facility Picture

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

(To top of page)

Subsequent License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone

Scheduled

Actual

Receive Subsequent License Renewal Application (SLRA)

04/2024

04/17/2024

Publish Federal Register Notice (FRN) – SLRA Availability

04/2024

05/07/2024

Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing

06/2024

06/24/2024

Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping

08/2024

08/05/2024

Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping

08/2024

08/20/2024

Deadline for Filing Hearing Requests and Petitions for Intervention

08/2024 

08/23/2024 

Environmental Scoping Period Ends

09/2024

09/04/2024

Issue Draft Supplemental Environmental Impact Statement (SEIS)

06/2025

05/21/2025

Draft SEIS Comment Period Ends

07/2025

07/14/2025

Issue Safety Evaluation

09/2025

09/09/2025

Issue Final SEIS

09/2025

09/03/2025

U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS

09/2025

09/12/2025

Decision – Director, Office of Nuclear Reactor Regulation

11/13/2025

 

*Schedule change letter 08/07/2025

(To top of page)

Environmental Review

NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 17, Second Renewal, Regarding Subsequent License Renewal for Dresden Nuclear Power Station, Units 2 and 3- Final Report was published on September 3, 2025. This supplement documents the NRC staff's review of the environmental issues at Dresden Nuclear Power Station, Units 2 and 3, regarding the Constellation Energy Generation, LLC’s application for subsequent license renewal of that facility. This supplement was prepared in accordance with 10 Part 51 and NUREG-1437, Revision 2, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Final Report,” dated August 2024. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (subsequent license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's preliminary recommendation regarding the proposed action.

Safety Evaluation

The NRC staff reviewed the Dresden Nuclear Power Station, Units 2 and 3, subsequent license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants" and prepared a safety evaluation to document its findings. The “Final Safety Evaluation to the SLRA of Dresden Nuclear Power Station, Units 2 and 3," was issued on September 9, 2025.
 

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, as applicable, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
 

Date

Description

08/20/2024

Meetings to discuss the subsequent license renewal process and environmental scoping for Dresden Units 2 and 3

05/30/2025

Draft Supplemental Environmental Impact Statement (DSEIS)

FRN (90 FR 23079) issued for public comment

DSEIS public comments may be submitted by July 14, 2025, by:

  • Going to Regulations.gov
  • Emailing DresdenEnvironmental.Resource@nrc.gov
  • Mailing:
         U.S. Nuclear Regulatory Commission
         Office of Administration
         ATTN: Program Management, Announcements and Editing Staff
         Mail Stop: TWFN-7-A60M
         Washington, DC 20555-0001

(To top of page)

Project Managers

Dresden Nuclear Power Stations PMs

License Renewal (Safety)

Mark Yoo

License Renewal (Environmental)

Angela Sabet

Lead Power Plant

Surinder Arora