Skip to main content

Spotlight

H.B. Robinson Steam Electric Plant, Unit 2 – Subsequent License Renewal Application

On this page

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

License Renewal Review Schedule*

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Scheduled Actual
Receive Subsequent License RenewalApplication (SLRA) 04/2025 04/01/2025
Publish Letter – SLRA Availability 04/2025 04/08/2025
Publish Letter – Docketing Acceptance/Rejection and Opportunity for Hearing 05/2025 04/28/2025
Publish Federal Register Notice FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 05/2025 05/22/2025
Environmental Scoping Period Ends 06/2025 06/23/2025
Deadline for Filing Hearing Requests and Petitions for Intervention 07/2025 07/07/2025
Issue Draft Supplemental Environmental Impact Statement (SEIS) 12/2025 12/22/2025
Draft SEIS Comment Period Ends 01/2026 02/23/2026
Issue Final SEIS 03/2026 3/12/2026
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 03/2026 3/20/2026
Issue Safety Evaluation Report 04/2026 04/01/2026
Decision – Director, Office of Nuclear Reactor Regulation 04/2026 04/23/2026

To top of page

Environmental Review

Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 13, Second Renewal, Regarding Subsequent License Renewal for H.B. Robinson Steam Electric Plant, Unit No. 2, Final Report, was made publicly available on March 12, 2026. The final supplemental environmental impact statement documents the NRC staff’s review of the environmental impacts of subsequent license renewal for H.B. Robinson Steam Electric Plant, Unit No. 2. The final supplemental environmental impact statement was prepared in accordance with 10 CFR Part 51 and documents the NRC staff’s analysis that considers and weighs the environmental effects of the proposed action (subsequent license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff’s recommendation regarding the proposed action: The NRC staff’s recommendation is that the adverse environmental impacts of subsequent license renewal for Robinson are not so great that preserving the option of subsequent license renewal for energy-planning decision-makers would be unreasonable.

Safety Evaluation

The NRC staff reviewed the H.B. Robinson Steam Electric Plant, Unit 2, subsequent license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants" and prepared a safety evaluation to document its findings. The “Safety Evaluation Related to the Subsequent License Renewal of H.B. Robinson Steam Electric Plant, Unit 2," was issued on April 1, 2026.

 

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

To top of page

Project Managers

H.B. Robinson Steam Electric Plant, Unit 2 PMs
License Renewal (Safety) Mark Yoo
License Renewal (Environmental) Karen Loomis
Lead Power Plant Natreon Jordan

To top of page

Page Last Reviewed/Updated Thursday, April 23, 2026