R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Application

Image of R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Application

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

(To top of page)

Subsequent License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the ;NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 06/2026 06/17/2026
Publish Federal Register Notice (FRN) – SLRA Availability 06/2026 06/24/2026
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 07/2026 07/16/2026
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping TBD  
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping TBD  
Environmental Scoping Period Ends TBD  
Deadline for Filing Hearing Requests and Petitions for Intervention TBD  
Issue Draft Supplemental Environmental Impact Statement (DSEIS) TBD  
End of DSEIS Comment Period TBD  
Issue Safety Evaluation Report TBD  
Issue Final SEIS TBD  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS TBD  
Decision – Director, Office of Nuclear Reactor Regulation TBD  

 

(To top of page)

Environmental Review

 

(To top of page)

Safety Evaluation

 

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date Description
09/11/2025

Pre-application public meetings to discuss the license renewal process with Constellation Energy, LLC for the R.E. Ginna Nuclear Power Plant

(To top of page)

Project Managers

R.E. Ginna Nuclear Power Plant PMs
License Renewal (Safety) Brian Harris 
License Renewal (Environmental) Angela Sabet
Lead Power Plant V. Sreevinas