Duane Arnold Energy Center - License Renewal Application

Renewed License Issued on 12/16/2010

On this page:

Application Information:

To top of page

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 10/01/08 10/01/08
Publish Federal Register Notice (FRN) - LRA availability 11/17/08 11/17/08
Publish FRN - acceptance/rejection and opportunity for hearing 02/17/09 02/17/09
Publish FRN - environmental scoping meeting 03/24/09 03/24/09
Deadline for filing hearing request and petition for intervention 04/20/09 04/20/09
Public Meeting License Renewal Overview and Environmental Scoping meeting 04/22/09 04/22/09
Environmental scoping period ends 05/25/09 05/25/09
Audit – Environmental 06/15/09 06/15/09
Audit – Scoping & Screening Audit Methodology 08/24/09 08/24/09
Audit – Aging Management Programs 08/10/09 08/10/09
Publish FRN - draft SEIS available for comments 01/29/10 02/19/10
Public Meeting - draft SEIS meeting 03/31/10 03/31/10
Issue safety evaluation report (SER) with open items 05/10/10 05/07/10
End of draft SEIS comment period 04/19/10 04/19/10
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 06/08/10 06/08/10
Issue final SER 09/03/10 09/02/10
ACRS full committee meeting 10/07/10 10/07/10
Issue final SEIS 10/08/10 10/07/10
U.S. Environmental Protection Agency FRN Published - availability of final SEIS 10/15/10 10/15/10
Commission decision (30 months if hearing) 12/16/10 12/16/10

To top of page

Environmental Impact Statement

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Duane Arnold Energy Center (NUREG-1437, Supplement 42) Final Report," was published in October 2010. This supplement documents the NRC's review of the environmental issues at Duane Arnold Energy Center, regarding the NextEra Energy Duane Arnold, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71 and 10 CRF 51.91. This supplemental environmental impact statement includes the NRC’s analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC’s recommendation regarding the proposed action.

To top of page

Safety Evaluation Report

The NRC staff reviewed the Duane Arnold Energy Center license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued on May 7, 2010, as "Safety Evaluation Report Related to the License Renewal of Duane Arnold Energy Center."

Subsequently, on September 2, 2010 the document "Safety Evaluation Report Related to the License Renewal of Duane Arnold Energy Center" was issued.

In November 2010, the report "Safety Evaluation Report Related to the License Renewal of Duane Arnold Energy Center" was issued as NUREG-1955.

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Public Meetings Related to Environmental Review

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
04/22/2009

Meeting to discuss the environmental scoping process for the License Renewal review of the Duane Arnold Energy Center.

To top of page

Project Managers for Duane Arnold Energy Center

Duane Arnold Energy Center PMs
License Renewal Brian Harris
License Renewal Jeremy Susco
Lead Power Plant Peter Tam