Application Information

Note: The V.C. Summer subsequent license renewal application (SLRA) is contained in ADAMS Package ML23233A179

To top of page

License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 08/2023 08/17/2023
Publish Federal Register Notice (FRN) – SLRA Availability 09/2023 09/11/2023
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 10/2023 10/16/2023
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 10/2023  11/03/2023
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping 11/2023 11/09/2023 11/14/2023 
Environmental Scoping Period Ends 11/2023 12/04/2023 
Deadline for Filing Hearing Requests and Petitions for Intervention 12/2023 12/15/2023
Issue Draft Site-Specific Environmental Impact Statement (EIS) 11/2024  
Public Meeting – Draft EIS Meeting 12/2024  
End of Draft EIS Comment Period 01/2025  
Issue Safety Evaluation Report 01/2025  
Advisory Committee on Reactor Safeguards Full Committee Meeting 03/2025  
Issue Final EIS 06/2025  
U.S. Environmental Protection Agency FRN Published – Availability of Final EIS 06/2025  
Decision – Director, Office of Nuclear Reactor Regulation 08/2025  

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
 

Date Description
11/03/2023 Notice of Intent To Conduct Scoping Process and Prepare Environmental Impact Statement; Dominion Energy South Carolina, Inc.; Virgil C. Summer Nuclear Station, Unit 1 (88 FR 75627)
11/09/2023 Virtual public meeting to discuss the license renewal process and environmental scoping for Virgil C. Summer Nuclear Station
11/14/2023 In-person public meeting to discuss the license renewal process and environmental scoping for Virgil C. Summer Nuclear Station

To top of page

Project Managers for Virgil C. Summer, Unit 1

V.C. Summer PMs
License Renewal (Safety) Marieliz Johnson
License Renewal (Environmental) Kim Conway
Lead Power Plant Ed Miller