License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 04/2024 04/17/2024
Publish Federal Register Notice (FRN) – SLRA Availability 04/2024 05/07/2024
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 06/2024 06/24/2024
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 08/2024  
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping 08/2024  
Deadline for Filing Hearing Requests and Petitions for Intervention 08/2024  08/23/2024 
Environmental Scoping Period Ends 09/2024  
Issue Draft Supplemental Environmental Impact Statement (SEIS) 06/2025  
Public Meeting – Draft SEIS Meeting, If Needed TBD  
Draft SEIS Comment Period Ends 07/2025  
Issue Safety Evaluation 09/2025  
Issue Final SEIS 10/2025  
Advisory Committee on Reactor Safeguards Full Committee Meeting 11/2025  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 11/2025  
Decision – Director, Office of Nuclear Reactor Regulation 12/2025  

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

(To top of page)

Project Managers

Dresden Nuclear Power Stations PMs
License Renewal (Safety) Mark Yoo
License Renewal (Environmental) Tam Tran
Lead Power Plant Surinder Arora

(To top of page)