Dresden Nuclear Power Station, Units 2 and 3 – Subsequent License Renewal Application
On this page:

Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Subsequent License Renewal Review Schedule
These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestone |
Scheduled |
Actual |
Receive Subsequent License Renewal Application (SLRA) |
04/2024 |
04/17/2024 |
Publish Federal Register Notice (FRN) – SLRA Availability |
04/2024 |
05/07/2024 |
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing |
06/2024 |
06/24/2024 |
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping |
08/2024 |
08/05/2024 |
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping |
08/2024 |
08/20/2024 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
08/2024 |
08/23/2024 |
Environmental Scoping Period Ends |
09/2024 |
09/04/2024 |
Issue Draft Supplemental Environmental Impact Statement (SEIS) |
06/2025 |
05/21/2025 |
Draft SEIS Comment Period Ends |
07/2025 |
07/14/2025 |
Issue Safety Evaluation |
09/2025 |
|
Issue Final SEIS |
10/2025 |
|
Advisory Committee on Reactor Safeguards Full Committee Meeting |
11/2025 |
|
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS |
11/2025 |
|
Decision – Director, Office of Nuclear Reactor Regulation |
12/2025 |
|

Environmental Review
NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 17, Second Renewal, Regarding Subsequent License Renewal for Dresden Nuclear Power Station, Units 2 and 3- Draft Report for Comment was published on May 21, 2025, for public comment. This supplement documents the NRC staff's review of the environmental issues at Dresden Nuclear Power Plant, Units 2 and 3, regarding the Constellation Energy Generation, LLC’s application for subsequent license renewal of that facility. This supplement was prepared in accordance with 10 Part 51 and NUREG-1437, Revision 2, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Final Report,” dated August 2024. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (subsequent license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's preliminary recommendation regarding the proposed action. The comment period ends July 14, 2025.
Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, as applicable, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Date |
Description |
08/20/2024 |
Meetings to discuss the subsequent license renewal process and environmental scoping for Dresden Units 2 and 3
|
05/30/2025 |
Draft Supplemental Environmental Impact Statement (DSEIS)
FRN (90 FR 23079) issued for public comment
DSEIS public comments may be submitted by July 14, 2025, by:
|

Project Managers
Dresden Nuclear Power Stations PMs |
License Renewal (Safety) |
Mark Yoo |
License Renewal (Environmental) |
Angela Sabet |
Lead Power Plant |
Surinder Arora |