Arkansas Nuclear One, Unit 1- License Renewal Application

Renewed License Issued 06/20/2001

Arkansas Nuclear One Picture

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

(To top of page)

License Renewal Review Schedule

Milestones Schedule Date Actual Date
Receive License Renewal Application 02/01/00 02/01/00
FRN Published for Receipt & Acceptability 02/15/00 02/11/00
FRN Published for Acceptance/Rejection/ Opportunity for Hearing of LRA 03/03/00 03/03/00
FRN Published for Intent/Environmental Scoping Mtg 03/06/00 03/10/00
Deadline for Filing Hearing Requests and Petitions for Intervention 04/03/00 04/03/00
Environmental Scoping Meeting 04/04/00 04/04/00
Environmental Scoping Period Ends 05/09/00 05/09/00
Environmental RAIs Issued 06/23/00 06/05/00
Safety RAIs Issued 06/29/00 06/21/00
Environmental RAI Responses Received 08/18/00 08/08/00
Safety RAI Responses Received 09/12/00 09/12/00
Scoping Inspection Complete 12/01/00 12/15/00
Draft Supplemental Environmental Impact Statement Issued 12/05/00 10/03/00
FRN Published for Availability/Comment of Draft SEIS 12/05/00 10/03/00
SER with Open Items Issued 01/10/01 01/10/01
Public Mtg to Discuss Draft SEIS 01/15/01 11/14/00
ACRS Subcommittee Mtg on SER with Open Items 02/22/01 02/22/01
Aging Management Review Inspection Complete 02/16/01 02/09/01
ACRS Full Committee Mtg on SER with Open Items 03/01/01 03/01/01
End of Draft SEIS Comment Period 02/26/01 01/04/01
SER Open Item Responses Received 05/10/01 03/14/01
Final SEIS Issued 04/26/01 04/15/01
FRN Published for Availability of Final SEIS 04/26/01 04/15/01
Optional Final Inspection Complete not required ---
SER Issued 04/13/01 04/12/01
Regional Administrator's Letter Issued 05/07/01 05/04/01
ACRS Subcommittee Mtg on SER not required ---
ACRS Full Committee Mtg on SER 05/10/01 05/10/01
ACRS Letter Issued 05/18/01 05/18/01
Commission Paper with Staff Recommendations 05/21/01 05/21/01
Commission Decision 06/22/01 06/12/01

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

(To top of page)

Environmental Impact Statement

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Supplement 3, Regarding Arkansas Nuclear One, Unit 1, was published April 2001.

This supplement documents the NRC staff's review of the environmental issues at the Arkansas Nuclear One, Unit 1 in support of Entergy Operations, Inc.'s application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.

(To top of page)

Safety Evaluation Report

The NRC staff reviewed the ANO-1 license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was first issued in January 2001, as "Safety Evaluation Report with open items related to the License Renewal of Arkansas Nuclear One, Unit 1." The report is available in ADAMS under accession number ML010110042.

In April 2001, the "Final Safety Evaluation Report related to the License Renewal of Arkansas Nuclear One, Unit 1" was issued as NUREG-1743.