Perry Nuclear Power Plant Unit 1 – License Renewal Application

On this page:
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

License Renewal Review Schedule
These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal Application (LRA) |
07/2023 |
07/03/2023 |
Publish Federal Register Notice (FRN) – LRA Availability |
08/2023 |
08/09/2023 |
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing |
09/2023 |
09/29/2023 |
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping |
09/2023 |
10/10/2023 |
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping |
10/2023 |
10/19/2023 |
Environmental Scoping Period Ends |
10/2023 |
11/09/2023 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
11/2023 |
11/28/2023 |
Issue Draft Supplemental Environmental Impact Statement (SEIS) |
08/2024 |
08/30/2024 |
Public Meeting – Draft SEIS Meeting, If Needed |
09/2024 |
|
End of DSEIS Comment Period |
10/2024 |
|
Issue Safety Evaluation Report (SER) |
03/2025 |
|
ACRS Subcommittee Meeting |
N/A |
|
Issue Final SEIS |
04/2025 |
|
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS |
05/2025 |
|
ACRS Full Committee Meeting |
05/2025 |
|
Decision – Director, NRR |
08/2025 |
|

Environmental Review
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Supplemental 61, Regarding License Renewal of Perry Nuclear Power Plant, Draft Report for Comment," was published August 2024. This supplement documents the NRC staff's review of the environmental issues at the Perry Nuclear Power Plant, Unit 1, in support of its license renewal application of that facility. This draft environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed action.

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Date |
Description |
10/19/2023 |
Meeting to conduct a scoping process to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the potential license renewal of the operating license for Perry Nuclear Power Plant, Unit 1.
Meeting Feedback
|

Project Managers for Perry Unit 1
Perry Unit 1 PMs |
License Renewal (Safety) |
Vaughn Thomas |
License Renewal (Environmental) |
Lance Rakovan |
Lead Power Plant |
Scott Wall |
