*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 12/18/08 12/18/08
Publish Federal Register Notice (FRN) - LRA availability 02/04/09 02/04/09
Publish FRN - acceptance and opportunity for hearing 03/09/09 03/09/09
Publish FRN - environmental scoping meeting 03/30/09 03/30/09
Audit – Environmental 07/20/09-
07/24/09
7/20/09-
07/24/09
Public Meeting - License Renewal Overview and Environmental Scoping meeting 04/16/09 04/16/09
Deadline for filing hearing requests and petitions for intervention 05/08/09 05/08/09
Environmental scoping period ends 06/08/09 06/08/09
Audit – Scoping & Screening Audit Methodology 06/22/09-
06/26/09
06/22/09-
06/26/09
Audit – Aging Management Programs 07/13/09-
07/17/09
07/13/09-
07/17/09
Issue safety evaluation report (SER) with open items 12/10/10 12/14/10
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 01/12/11 01/12/11
Issue draft supplemental environmental impact statement (SEIS) 05/11 05/26/11
Public Meeting - draft SEIS meeting 06/28/11 06/28/11
End of draft SEIS comment period 07/25/11 07/25/11
Application withdrawn by Licensee 02/06/13 02/06/13

* The review schedule was revised as described in the letters below:

To top of page

Environmental Impact Statement

NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Crystal River Unit 3 Nuclear Generating Plant (NUREG-1437, Supplement 44) Draft Report for Comment,” was published in May 2011. This supplement documents the NRC staff’s review of the environmental issues at Crystal River Unit 3 Nuclear Generating Plant regarding the Florida Power Corporation application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff’s analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC staff’s preliminary recommendation regarding the proposed action.

Since the licensee has withdrawn its application, all activities associated with NUREG-1437, Supplement 44, have ceased.

To top of page

Safety Evaluation Report

The NRC staff reviewed the Crystal River Unit 3 Nuclear Generating Plant license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on December 14, 2010, as "Safety Evaluation Report with Open Items Related to the License Renewal of Crystal River Unit 3 Nuclear Generating Plant."

Since the licensee has withdrawn its application, all activities associated with this Safety Evaluation Report have ceased.

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Public Meetings Related to Environmental Review

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
06/28/2011

Meeting to discuss the preliminary results of the environmental review for Crystal River Unit 3.

To top of page

Project Managers for Crystal River

Crystal River Station PMs
License Renewal (Safety) John Daily
License Renewal (Environmental) Elaine Keegan
Lead Power Plant Farideh Saba

To top of page

Page Last Reviewed/Updated Friday, August 28, 2020