Prairie Island Nuclear Generating Plant, Units 1 and 2 - License Renewal Application
Renewed Licenses Issued on June 27, 2011

On this page:
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
04/15/08 |
04/15/08 |
Federal Register Notice (FRN) Published- Receipt & Availability |
05/31/08 |
05/06/08 |
FRN Published - Acceptability/Opportunity for Hearing |
06/13/08 |
06/17/08 |
FRN Published - Notice of Intent to Conduct Environmental Scoping |
06/17/08 |
07/22/08 |
Public Meeting - Process Overview and Environmental Scoping |
07/30/08 |
07/30/08 |
On-site Audit - Scoping & Screening Methodology |
08/04/08 |
08/04/08 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
08/13/08 |
08/18/08 |
On-site Audit - Environmental |
08/18/08 |
08/18/08 |
Environmental Scoping Period Ends |
09/22/08 |
09/22/08 |
On-site Audit - Aging Management |
09/08/08 |
09/08/08 |
Environmental Requests for Additional Information (RAIs) Issued |
09/24/08 |
10/23/08 |
Environmental RAIs - Response Received |
10/24/08 |
11/21/08 |
Safety RAIs - Issued |
11/15/08 |
12/18/08 |
Safety RAI - Responses Received |
12/14/08 |
01/20/09 |
Inspection - Regional |
01/12/09 |
01/12/09 |
Public Exit Meeting - Regional Inspections |
02/18/09 |
02/18/09 |
Draft Supplemental Environmental Impact Statement (SEIS) - Issued |
11/16/09 |
11/16/09 |
EPA FRN Published - Availability / Comment on draft SEIS |
11/27/09 |
11/27/09 |
End of draft SEIS Comment Period |
01/30/10 |
01/30/10 |
Public Meeting - draft SEIS |
12/16/09 |
12/16/09 |
Safety Evaluation Report (SER) with Open Items - Issued |
06/07/09 |
06/04/09 |
Inspection - Final Optional |
TBD |
N/A |
ACRS Subcommittee Meeting on SER with Open Items |
07/07/09 |
07/07/09 |
SER with Open Items - Responses Received |
08/07/09 |
08/21/09 |
SER - Issued |
10/22/09 |
10/16/09 |
Final SEIS - Issued |
04/29/11 |
05/13/11 |
EPA FRN Published - Availability of Final SEIS |
05/2011 |
05/20/11 |
ACRS Full Committee Meeting on SER |
12/03/09 |
12/03/09 |
Decision Director NRR - Approval (22 months if no hearing) |
06/2011 |
06/27/11 |

Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Prairie Island Nuclear Generating Plant, Units 1 and 2 (NUREG-1437, Supplement 39) -- Final Report," was published in May 2011. This supplement documents the NRC staff's review of the environmental issues at Prairie Island Nuclear Generating Plant, Units 1 and 2, regarding the Northern State Power Co. application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the Staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the Staff's preliminary recommendation regarding the proposed action.

Safety Evaluation Report
The NRC staff reviewed the Prairie Island Nuclear Generating Plant Units 1 and 2 license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on June 4, 2009, as "Safety Evaluation Report With Open Items Related to the License Renewal of Prairie Island Nuclear Generating Plant Units 1 and 2". Subsequently, on October 16, 2009, the document, "Safety Evaluation Report Related to the License Renewal of Prairie Island Nuclear Generating Plant, Units 1 and 2", was issued.
In August 2011, the staff published the final "Safety Evaluation Report Related to the License Renewal of Prairie Island Nuclear Generating Plant Units 1 and 2" as NUREG-1960.
In August 2011, the staff issued Supplement 1 to NUREG-1960, "Safety Evaluation Report Related to the License Renewal of Prairie Island Nuclear Generating Plant Units 1 and 2".

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers for Prairie Island, Units 1 and 2
Prairie Island Nuclear Generating Plant Project Managers |
License Renewal |
Rick Plasse |
License Renewal |
Elaine Keegan |
Lead Power Plant |
Tom Wengert |