Diablo Canyon - License Renewal Application

Current Application Submitted on 11/07/2023

Previous Application Withdrawn on 03/07/2018

On October 31, 2022, Pacific Gas and Electric sent in a letter to “Request to Resume Review of the Diablo Canyon Power Plant License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application.

On this page:

Application Information:

Current License Renewal Review Schedule

Milestones

Schedule Date

Actual Date

Receive License Renewal Application (LRA)

11/2023

11/07/2023

Publish Federal Register Notice (FRN) – LRA Availability

11/2023

11/20/2023

Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing

12/2023

12/19/2023 

Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping

01/2024

01/24/2024

Public Meeting – Overview of License Renewal Process and Environmental Scoping

02/2024
(Virtual)
&
02/2024
(In-Person)

02/01/2024
(Virtual)
&
02/08/2024
(In-Person)

Environmental Scoping Period Ends

02/2024

02/23/2024

Deadline for Filing Hearing Requests and Petitions for Intervention

03/2024

03/04/2024

Issue Draft Supplemental Environmental Impact Statement (SEIS)

10/2024

10/25/2024

Public Meeting – Draft SEIS Meeting

11/2024

11/14/2024
(virtual)
&
11/20/2024
(in-person)

End of DSEIS Comment Period

12/2024

12/16/2024

Issue Safety Evaluation Report (SER)

06/2025

06/05/2025

Issue Final SEIS

06/2025

06/20/2025

U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS

06/2025

06/27/2025

Decision – Director, NRR

08/2025

 

To top of page

Previous License Renewal Review Schedule*

Milestones

Schedule Date

Actual Date

Receive license renewal application (LRA)

11/24/09

11/24/09

Publish Federal Register Notice (FRN) - LRA availability

12/11/09

12/11/09

Publish FRN - acceptance and opportunity for hearing

01/21/10

01/21/10

Publish FRN - environmental scoping meeting

01/21/10

01/27/10

Audit – Environmental

04/19/10

04/19/10

Public Meeting - License Renewal Overview

02/09/10

02/09/10

Public Meeting – Environmental Scoping

03/03/10

03/03/10

Deadline for filing hearing requests and petitions for intervention

03/22/10

03/22/10

Environmental scoping period ends

04/12/10

04/12/10

Audit – Scoping & Screening Audit Methodology

03/15/10

03/15/10

Audit – Aging Management Programs

04/12/10

04/12/10

Issue safety evaluation report (SER) with open items

12/10/10

01/10/11

Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting

02/2011

02/09/11

Issue SER

06/2011

06/02/11

Publish Federal Register Notice – Environmental Scoping Meetings

07/2015

07/01/15

Public Meeting – Environmental Scoping Meetings

08/2015

08/05/15

Environmental Scoping Period Ends

08/2015

08/31/15

Audit – Environmental

09/2015

10/01/15

Audit – SAMA

09/2015

09/23/15

Issue Supplemental Safety Evaluation Report (SER)

TBD

 N/A*

Issue Draft Supplemental Environmental Impact Statement (SEIS)

TBD

 N/A*

Publish EPA FRN – Draft SEIS Available for Comment

TBD

 N/A*

Public Meeting – Draft SEIS Meeting

TBD

 N/A*

End of Draft SEIS Comment Period

TBD

 N/A*

ACRS Subcommittee Meeting

TBD

 N/A*

ACRS Full Committee Meeting

TBD

 N/A*

Issue Final SEIS

TBD

 N/A*

Publish EPA FRN – Availability of Final SEIS

TBD

 N/A*

License Renewal decision

TBD

 N/A*

* previous application was withdrawn on March 7, 2018

Note: The preview review schedule was revised as described in the letters below:

To top of page

Environmental Review

NUREG-1437, Supplement 62, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2, Final Report" was made publicly available on June 20, 2025. The final supplemental environmental impact statement documents the NRC staff’s review of the environmental impacts of license renewal for Diablo Canyon Units 1 and 2. The final supplemental environmental impact statement was prepared in accordance with 10 CFR Part 51 and documents the NRC staff’s analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff’s recommendation regarding the proposed action: The NRC staff’s recommendation is that the adverse environmental impacts of license renewal for Diablo Canyon are not so great that preserving the option of license renewal for energy-planning decision-makers would be unreasonable.

To top of page

Safety Evaluation Report

The NRC staff reviewed the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared a report to document its findings. The “Safety Evaluation Related to the License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2”  was issued on June 5, 2025.

To top of page

Public Involvement

The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date

Description

11/20/2024

In-person public meeting to receive comments on the draft supplemental environmental impact statement

11/14/2024

Virtual public meeting to receive comments on the draft supplemental environmental impact statement

02/08/2024

Meeting (In-person) to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the license renewal of the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2.

02/01/2024

Meeting (Virtual) to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the license renewal of the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2.

08/05/2015

 

Meeting to discuss license renewal status and conduct environmental scoping for Diablo Canyon Power Plant, Units 1 and 2.

03/03/2010

 

Meeting to discuss environmental scoping for Diablo Canyon Power Plant, Units 1 and 2.

02/09/2010

Meeting to discuss the license renewal process for Diablo Canyon Power Plant, Units 1 and 2.