Diablo Canyon - License Renewal Application

Current Application Submitted on 11/07/2023

Previous Application Withdrawn on 03/07/2018

On October 31, 2022, Pacific Gas and Electric sent in a letter to “Request to Resume Review of the Diablo Canyon Power Plant License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application.

On this page:

Application Information:

Current License Renewal Review Schedule

Milestones Schedule Date Actual Date
Receive License Renewal Application (LRA) 11/2023 11/07/2023
Publish Federal Register Notice (FRN) – LRA Availability 11/2023 11/20/2023
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 12/2023 12/19/2023 
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 01/2024 01/24/2024
Public Meeting – Overview of License Renewal Process and Environmental Scoping 02/2024
(Virtual)
&
02/2024
(In-Person)
02/01/2024
(Virtual)
&
02/08/2024
(In-Person)
Environmental Scoping Period Ends 02/2024 02/23/2024
Deadline for Filing Hearing Requests and Petitions for Intervention 03/2024 03/04/2024
Issue Draft Supplemental Environmental Impact Statement (SEIS) 10/2024 10/25/2024
Public Meeting – Draft SEIS Meeting 11/2024 11/14/2024
(virtual)
&
11/20/2024
(in-person)
End of DSEIS Comment Period 12/2024 12/16/2024
Issue Safety Evaluation Report (SER) 06/2025  
Issue Final SEIS 06/2025  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 06/2025  
ACRS Full Committee Meeting 07/2025  
Decision – Director, NRR 08/2025  

To top of page

Previous License Renewal Review Schedule*

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 11/24/09 11/24/09
Publish Federal Register Notice (FRN) - LRA availability 12/11/09 12/11/09
Publish FRN - acceptance and opportunity for hearing 01/21/10 01/21/10
Publish FRN - environmental scoping meeting 01/21/10 01/27/10
Audit – Environmental 04/19/10 04/19/10
Public Meeting - License Renewal Overview 02/09/10 02/09/10
Public Meeting – Environmental Scoping 03/03/10 03/03/10
Deadline for filing hearing requests and petitions for intervention 03/22/10 03/22/10
Environmental scoping period ends 04/12/10 04/12/10
Audit – Scoping & Screening Audit Methodology 03/15/10 03/15/10
Audit – Aging Management Programs 04/12/10 04/12/10
Issue safety evaluation report (SER) with open items 12/10/10 01/10/11
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 02/2011 02/09/11
Issue SER 06/2011 06/02/11
Publish Federal Register Notice – Environmental Scoping Meetings 07/2015 07/01/15
Public Meeting – Environmental Scoping Meetings 08/2015 08/05/15
Environmental Scoping Period Ends 08/2015 08/31/15
Audit – Environmental 09/2015 10/01/15
Audit – SAMA 09/2015 09/23/15
Issue Supplemental Safety Evaluation Report (SER) TBD  N/A*
Issue Draft Supplemental Environmental Impact Statement (SEIS) TBD  N/A*
Publish EPA FRN – Draft SEIS Available for Comment TBD  N/A*
Public Meeting – Draft SEIS Meeting TBD  N/A*
End of Draft SEIS Comment Period TBD  N/A*
ACRS Subcommittee Meeting TBD  N/A*
ACRS Full Committee Meeting TBD  N/A*
Issue Final SEIS TBD  N/A*
Publish EPA FRN – Availability of Final SEIS TBD  N/A*
License Renewal decision TBD  N/A*

* previous application was withdrawn on March 7, 2018

Note: The preview review schedule was revised as described in the letters below:

To top of page

Environmental Review

NUREG-1437, Supplement 62, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2, Draft Report for Comment," was published October 25, 2024. This supplement documents the NRC staff's review of the environmental issues at Diablo Canyon Units 1 and 2 in support of the license renewal application. This draft supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed action.

To top of page

Previous Safety Evaluation Report

The NRC staff reviewed the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on January 10, 2011, as "Safety Evaluation Report with Open Items Related to the License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2."

Subsequently, on June 2, 2011, the document "Safety Evaluation Report Related to the License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2" was issued.

To top of page

Public Involvement

The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date Description
02/08/2024 Meeting (In-person) to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the license renewal of the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2.
02/01/2024 Meeting (Virtual) to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the license renewal of the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2.

08/05/2015

 

Meeting to discuss license renewal status and conduct environmental scoping for Diablo Canyon Power Plant, Units 1 and 2.

03/03/2010

 

Meeting to discuss environmental scoping for Diablo Canyon Power Plant, Units 1 and 2.

02/09/2010

Meeting to discuss the license renewal process for Diablo Canyon Power Plant, Units 1 and 2.

To top of page

Page Last Reviewed/Updated Wednesday, November 13, 2024