Oconee Nuclear Station, Units 1, 2, and 3 – Subsequent License Renewal Application

photo of Oconee Nuclear Station

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

 
Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 06/2021 06/07/2021
Publish Federal Register Notice (FRN) – SLRA Availability 06/2021 06/25/2021
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 07/2021 07/28/2021
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 08/2021  
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping 09/2021  
Environmental Scoping Period Ends 09/2021  
Deadline for Filing Hearing Requests and Petitions for Intervention 09/2021  
Issue Draft Supplemental Environmental Impact Statement (DSEIS) 05/2022  
Public Meeting – Draft SEIS Meeting, If Needed 06/2022  
End of DSEIS Comment Period 06/2022  
Issue Safety Evaluation Report 08/2022  
Advisory Committee on Reactor Safeguards Full Committee Meeting 10/2022  
Issue Final SEIS 12/2022  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 12/2022  
Decision – Director, Office of Nuclear Reactor Regulation 01/2023  

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers for Oconee, Units 1, 2, and 3

Oconee PMs
License Renewal (Safety) Angela Wu
License Renewal (Environmental) Lance Rakovan
Lead Power Plant Shawn Williams

To top of page

Page Last Reviewed/Updated Wednesday, August 04, 2021

Section Navigation