Oconee Nuclear Station, Units 1, 2, and 3 – Subsequent License Renewal Application

photo of Oconee Nuclear Station

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

 
Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 06/2021 06/07/2021
Publish Federal Register Notice (FRN) – SLRA Availability 06/2021 06/25/2021
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 07/2021 07/28/2021
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 08/2021 08/10/2021
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping 09/2021 08/25/2021
Environmental Scoping Period Ends 09/11/2021 09/11/2021
Deadline for Filing Hearing Requests and Petitions for Intervention 09/2021 09/27/2021
Issue Draft Supplemental Environmental Impact Statement (DSEIS) To be determined (TBD)*  
Public Meeting – Draft SEIS Meeting, If Needed TBD*  
End of DSEIS Comment Period TBD*  
Issue Safety Evaluation Report 12/2022  
Advisory Committee on Reactor Safeguards Full Committee Meeting 02/2023  
Issue Final SEIS TBD*  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS TBD*  
Decision – Director, Office of Nuclear Reactor Regulation TBD*  

To top of page

* : On February 24, 2022, the NRC Commission issued three orders (CLI-22-02, CLI-22-03, and CLI-22-04) and Staff Requirements Memorandum, SECY-21-0066, "Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses – Environmental Review," that impact the subsequent license renewal of the following plants:

  • Turkey Point, Units 3 and 4;
  • Peach Bottom, Units 2 and 3;
  • North Anna, Units 1 and 2;
  • Point Beach, Units 1 and 2;
  • Oconee Units, 1, 2, and 3; and
  • St. Lucie, Units, 1 and 2.

Until further notice, the completion date of specific milestones in the table above is undetermined and will be updated as soon as possible.

 

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers for Oconee, Units 1, 2, and 3

Oconee PMs
License Renewal (Safety) Angela Wu
License Renewal (Environmental) Lance Rakovan
Lead Power Plant Shawn Williams