Braidwood Nuclear Stations, Units 1 and 2 - License Renewal Application

Byron Facility
Renewed License Issued on 11/19/2015
  Braidwood Facility
Renewed License Issued on 01/27/2016
 

On this page:

Application Information:

To top of page

License Renewal Review Schedule*

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 05/29/13 05/29/13
Publish Federal Register Notice (FRN) – LRA availability 06/2013 06/13/13
Publish FRN – acceptance/rejection and opportunity for hearing 07/2013 07/24/13
Publish FRN – environmental scoping meeting 07/2013 08/06/13
Audit – Scoping & Screening Methodology 1 (at Byron) 07/2013 07/20/13
Audit – Aging Management Programs 1 (at Byron) 08/2013 08/20/13
Public Meeting - License Renewal Overview and Environmental Scoping meetings 08/20/13-08/21/13 08/20/13
(Byron)
08/21/13
(Braidwood)
Deadline for filing hearing requests and petitions for intervention 09/2013 09/23/13
Audit – Environmental (Byron) 09/2013 09/19/13
Environmental scoping period ends* 09/2013 09/27/13
Audit – Scoping & Screening Methodology 2 (at Braidwood) 10/2013 12/02/13-12/04/13
Audit – Aging Management Programs 2 (at Braidwood) 10/2013 12/02/13-12/06/13
Audit – Environmental (Braidwood) 11/2013 11/19/13
Regional Inspection (Byron) 08/2014 08/04/14-08/08/14
and 08/22/14
Regional Inspection (Braidwood) 09/2014 09/15/14-09/26/14
Issue safety evaluation report (SER) with open items 11/2014 10/30/14
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 12/2014 12/03/14
Issue draft supplemental environmental impact statement (SEIS) - Byron 12/2014 12/31/14
Publish FRN – Byron draft SEIS available for comments 01/2015 01/02/15
Public Meeting – Byron draft SEIS meeting 02/2015 02/03/15
End of draft SEIS comment period – Byron 02/2015 02/20/15
Issue draft SEIS - Braidwood 03/2015 03/18/15
Publish FRN – Braidwood draft SEIS available for comments 03/2015 03/25/15
Public Meeting – Braidwood draft SEIS meeting 04/2015 04/21/15
End of draft SEIS comment period – Braidwood 05/2015 05/12/15
Issue final SER 07/2015 07/06/15
Issue final SEIS – Byron 07/2015 07/15/15
U.S. Environmental Protection Agency FRN Published – availability of final SEIS – Byron 08/2015 07/24/15
ACRS full committee meeting 09/2015 09/10/15
Issue final SEIS – Braidwood 11/2015 11/12/15
U.S. Environmental Protection Agency FRN Published – availability of final SEIS – Braidwood 11/2015 11/27/15
Decision – Director, NRR – Bryon 11/2015 11/19/15 
Decision – Director, NRR – Braidwood 01/2016 01/27/16 
Commission decision, if hearing granted TBD  

The NRC has documented the results of the environmental scoping period in the Byron Scoping Summary Report and Braidwood Scoping Summary Report.

Note: The Byron and Braidwood Nuclear Stations, Units 1 and 2, review schedule was revised as described in the letter below:

To top of page

Safety Evaluation Report

The NRC staff reviewed the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on October 30, 2014, as "Safety Evaluation Report with Open Items Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2."

Subsequently, on July 6, 2015, the staff issued the document "Safety Evaluation Report Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2."

In December 2015, the staff published the final "Safety Evaluation Report Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2" as NUREG-2190.

To top of page

Environmental Impact Statements

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron Station, Units 1 and 2 (NUREG-1437, Supplement 54) Final Report," was published in July 2015. This supplement documents the NRC staff's review of the environmental issues at Byron Station, Units 1 and 2 regarding the Exelon Generation Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's recommendation regarding the proposed action.

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood Station, Units 1 and 2, (NUREG-1437, Supplement 55) Final Report," was published in November 2015. This supplement documents the NRC staff's review of the environmental issues at Braidwood Station, Units 1 and 2, regarding the Exelon Generation Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's recommendation regarding the proposed action.

To top of page

Public Involvement

The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
04/21/2015

Meeting to discuss draft environmental impact statement for Braidwood Nuclear Station.

02/03/2015

Meeting to discuss draft environmental impact statement for Byron Nuclear Station.

08/21/2013

Meeting to discuss the license renewal process and environmental scoping for Braidwood Nuclear Station.

08/20/2013

Meeting to discuss the license renewal process and environmental scoping for Byron Nuclear Station.