Pilgrim Nuclear Power Station - License Renewal Application
Renewed License Issued on May 29, 2012

On this page:
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

License Renewal Review Schedule*
* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
01/27/06 |
01/27/06 |
Federal Register Notice (FRN) Published - Receipt & Availability Review |
01/31/06 |
01/31/06 |
Public Information Meeting - LR Process & Safety Review Overview |
03/08/06 |
03/08/06 |
FRN Published - Acceptability/Opportunity for Hearing |
03/28/06 |
03/27/06 |
FRN Published - Intent/Environmental Scoping Meeting |
04/14/06 |
04/14/06 |
Environmental Site Audit |
05/01/06 |
05/01/06 |
Public Meeting - Environmental Scoping |
05/17/06 |
05/17/06 |
Audit - Aging Management Programs (AMPs) |
05/22/06 |
05/22/06 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
05/27/06 |
05/27/06 |
Audit - Scoping and Screening Methodology |
06/05/06 |
06/05/06 |
Public Exit Meeting - Scoping & Screening Methodology Audit |
07/19/06 |
07/19/06 |
Environmental Scoping Periods Ends |
06/16/06 |
06/16/06 |
Audit - Aging Management Reviews (AMRs) |
06/19/06 |
06/19/06 |
Environmental Requests for Additional information (RAIs) - Issued |
07/14/06 |
07/14/06 |
Public Exit Meeting - AMP/AMR Audit (Opt. 7/24-27/06) |
07/27/06 |
07/19/06 |
Environmental RAIs - Responses Received |
08/24/06 |
08/24/06 |
Safety RAIs - Issued |
09/10/06 |
09/08/06 |
Safety RAI - Responses Received |
10/10/06 |
10/06/06 |
Inspection - Scoping and Screening/AMP |
09/18-22/06 |
09/18-22/06 |
Public Exit Meeting - Scoping & Screening/AMP Inspections |
10/02-06/06 |
10/02-06/06 |
Draft Supplemental Environmental Impact Statement (SEIS) Issued |
12/08/06 |
12/08/06 |
FRN Published - Availability/Comment on draft SEIS |
12/15/06 |
12/14/06 |
Public Meeting - draft SEIS |
01/24/07 |
01/24/07 |
Public Exit Meeting - Scoping & Screening/AMP Inspections |
01/30/07 |
01/30/07 |
End of draft SEIS Comment Period |
02/28/07 |
02/28/07 |
Safety Evaluation Report (SER) with Open Item(s) - Issued |
03/01/07 |
03/01/07 |
ACRS Subcommittee Meeting on SER with Open Item(s) |
04/04/07 |
04/04/07 |
SER Open Item(s) - Response(s) Received |
05/01/07 |
05/01/07 |
SER - Issued |
07/01/07 |
06/28/07 |
Final SEIS - Issued |
07/27/07 |
07/27/07 |
FRN Published - Availability of Final SEIS |
08/03/07 |
08/03/07 |
ACRS Full Committee Meeting on SER |
09/06/07 |
09/06/07 |
Decision Director, NRR (license issued, if approved and no hearing is granted - 22 mo) |
N/A |
N/A |
Commission Decision (if hearing is granted - 30 months) |
TBD |
05/29/12 |

Environmental Impact Statements
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Final Supplement 29, regarding Pilgrim Nuclear Power Station Final Report, was published July 2007.
This supplement documents the NRC staff's review of the environmental issues at Pilgrim Nuclear Power Station regarding Entergy Nuclear Operations, Inc., application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.

Safety Evaluation Report
The NRC staff reviewed the Pilgrim license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued in March 1, 2007, as "Safety Evaluation Report with Open Items Related to the License Renewal of Pilgrim Nuclear Power Station".
In June 2007, the NRC staff issued the final report,"Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station." In September 2007, a supplement to the "Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station" was issued.
In November 2007, the report, "Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station", was issued as NUREG-1891. In June 2011, a supplement to the "Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station" was issued.

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.