Cooper Nuclear Station - License Renewal Application
Renewed License Issued on 11/29/2010

On this page:
Application Information:

License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
09/24/08 |
09/30/08 |
FRN Published- Receipt & Availability |
11/17/08 |
11/17/08 |
FRN Published – Acceptability and Opportunity for Hearing |
12/30/08 |
12/30/08 |
FRN Published-Notice of Intent to Conduct Environmental Scoping |
01/27/09 |
01/26/09 |
Public Meeting – LR Overview & Environmental Scoping |
02/25/09 |
02/25/09 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
02/23/09 |
02/23/09 |
Environmental Scoping Period Ends |
03/27/09 |
03/27/09 |
Audit – Environmental |
03/30/09–04/03/09 |
03/30/09 |
Audit - Aging Management Programs (AMPs/TLAAs/AMR) |
04/20–24/09 |
04/20/09 |
Environmental Requests for Additional Information (RAIs) Issued |
04/30/09 |
05/01/09 |
Audit - Scoping & Screening Methodology |
05/04–08/09 |
05/04/09 |
Environmental RAIs - Response Received |
06/01/09 |
05/18/09 |
Safety RAIs – Issued |
06/30/09 |
07/16/09 |
Inspection – Regional |
07/27–31/09 |
07/27/09 |
Safety RAI - Responses Received |
07/30/09 |
08/16/09 |
Public Exit Meeting - Regional Inspections |
04/07/10 |
04/07/10 |
Inspection – Final |
08/10–14/09 |
08/10/09 |
Draft Supplemental Environmental Impact Statement (SEIS) – Issued |
02/09/10 |
02/18/10 |
EPA FRN Published - Availability / Comment on draft SEIS |
02/26/10 |
02/26/10 |
Public Meeting - draft SEIS |
04/07/10 |
04/07/10 |
Safety Evaluation Report (SER) with Open Items – Issued* |
03/02/10 |
04/06/10 |
End of draft SEIS Comment Period |
05/05/10 |
05/05/10 |
ACRS Subcommittee Meeting on SER with Open Items |
05/05/10 |
05/05/10 |
Final SEIS – Issued |
07/30/10 |
07/30/10 |
EPA FRN Published - Availability of Final SEIS |
07/30/10 |
08/06/10 |
SER – Issued |
09/07/10 |
09/01/10 |
ACRS Full Committee Meeting on SER |
10/07/10 |
10/07/10 |
Staff Recommendation to Director, NRR |
10/22/10 |
11/19/10 |
Decision Director NRR - Approval (26 months if no hearing) |
11/29/10 |
11/29/10 |
Commission decision (if hearing is granted) |
07/15/11 |
N/A |

Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Cooper Nuclear Station (NUREG-1437, Supplement 41) Final Report," was published in July 2010. This supplement documents the NRC staff's review of the environmental issues at Cooper Nuclear Station, regarding the Nebraska Public Power District application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the Staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the Staff's recommendation regarding the proposed action.

Safety Evaluation Report
The NRC staff reviewed the Cooper Nuclear Station license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued on April 6, 2010, as "Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station."
On September 1, 2010, the NRC staff issued the final "Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station."
In October 2010, the report "Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station" was issued as NUREG-1944.

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers for Cooper Nuclear Station
Cooper Nuclear Station PMs |
License Renewal |
Tam Tran |
License Renewal |
Bennett Brady |
Lead Power Plant |
Fred Lyon |