Application Information:
Subsequent License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
| Milestone | Scheduled | Actual |
| Receive Subsequent License Renewal Application (SLRA) | 05/2026 | 05/07/2026 |
| Publish Letter—SLRA Availability | 05/2026 | 05/15/2026 |
| Publish Letter—Docketing Acceptance/Rejection and Opportunity for Hearing | 06/2026 | 06/05/2026 |
| Publish Federal Register Notice FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping | 06/2026 | |
| Environmental Scoping Period Ends | 07/2026 | |
| Deadline for Filing Hearing Requests and Petitions for Intervention | 08/2026 | |
| Issue Draft Supplemental Environmental Impact Statement (EIS) | 01/2027 | |
| Draft Supplemental EIS Comment Period Ends | 02/2027 | |
| Issue Final Supplemental EIS | 04/2027 | |
| Issue Safety Evaluation | 04/2027 | |
| Decision—Director, Office of Nuclear Reactor Regulation | 06/2027 |
Environmental Review
No Content at this time
Safety Evaluation Report
No Content at this time
Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Project Managers for Cooper Nuclear Station
| Cooper Nuclear Station PMs | |
|---|---|
| License Renewal (Safety) | Mark Yoo |
| License Renewal (Environmental) | Lance Rakovan |
| Lead Power Plant | Thomas Byrd |
Page Last Reviewed/Updated Monday, June 08, 2026