Palisades Nuclear Plant - License Renewal Application
Renewed License Issued 01/17/2007

On this page:
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

License Renewal Review Schedule*
* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
03/31/05 |
03/31/05 |
Federal Register Notice (FRN) Published – Receipt & Availability Review |
04/12/05 |
04/12/05 |
Public Information Meeting – LR Process & Safety Review Overview |
04/28/05 |
04/28/05 |
Receive License Renewal Application Supplement |
05/05/05 |
05/05/05 |
FRN Published – Acceptability/Opportunity for Hearing |
06/05/05 |
060/8/05 |
FRN Published – Intent/Environmental Scoping Meeting |
06/24/05 |
06/24/05 |
Public Exit Meeting – Scoping & Screening Methodology Audit |
07/01/05 |
07/01/05 |
Public Meeting – Environmental Scoping |
07/28/05 |
07/28/05 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
08/08/05 |
08/08/05 |
Environmental Scoping Periods Ends |
08/22/05 |
08/22/05 |
Public Exit Meeting – AMP/AMR Audit |
09/02/05 |
09/02/05 |
Environmental Requests for Additional information (RAIs) – Issued |
09/19/05 |
09/19/05 |
Environmental RAIs – Responses Received |
10/31/05 |
10/31/05 |
Public Exit Meeting – Scoping & Screening/AMP Inspections |
12/01/05 |
12/01/05 |
Safety RAIs – Issued |
12/09/05 |
11/30/05 |
Safety RAI – Responses Received |
01/09/05 |
01/13/06 |
Draft Supplemental Environmental Impact Statement (SEIS) Issued |
02/25/06 |
02/14/06 |
FRN Published – Availability/Comment on draft SEIS |
02/27/06 |
02/23/06 |
Public Meeting – draft SEIS |
04/05/06 |
04/05/06 |
End of draft SEIS Comment Period |
05/18/06 |
05/18/06 |
Safety Evaluation Report (SER) with Open Item(s) – Issued |
06/02/06 |
06/01/06 |
ACRS Subcommittee Meeting on SER with Open Item(s) |
07/11/06 |
07/11/06 |
SER Open Item(s) – Response(s) Received |
07/28/06 |
07/05/06 |
Final SEIS – Issued |
10/13/06 |
10/12/06 |
SER – Issued |
09/29/06 |
09/28/06 |
FRN Published – Availability of Final SEIS |
10/20/06 |
10/19/06 |
ACRS Full Committee Meeting on SER |
11/01/06 |
11/01/06 |
Decision – Director, NRR (license issued, if approved and no hearing is granted – 23 months) |
01/17/07 |
01/17/07 |

Environmental Impact Statements
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Supplement 27, regarding Palisades Nuclear Plant, was published October 2006.
This supplement documents the NRC staff's review of the environmental issues at Palisades regarding Nuclear Management Company, LLC's application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.

Safety Evaluation Report
The NRC staff reviewed the Palisades license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued June 1, 2006, as "Safety Evaluation Report With a Confirmatory Item Related to the License Renewal of the Palisades Nuclear Plant." The report is available in ADAMS under accession number ML061530042.
In January 2007, the report "Safety Evaluation Report Related to the License Renewal of Palisades Nuclear Plant" was issued as NUREG-1871. The report is available in ADAMS under accession numbers ML062710074.

Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers for Palisades Nuclear Plant
Palisades PMs |
License Renewal |
Juan Ayala |
Lead Power Plant |
L. Mark Padovan |
Environmental |
Bo Pham |