Receive license renewal application (LRA) |
12/09/14 |
12/09/14 |
Publish Federal Register Notice (FRN) – LRA availability |
12/18/14 |
12/18/14 |
Publish FRN – acceptance/rejection and opportunity for hearing |
01/30/15 |
02/03/15 |
Publish FRN – environmental scoping meeting |
02/03/15 |
02/03/15 |
Audit – Scoping & Screening Methodology |
03/09/15–03/12/15 |
03/09/15–03/12/15 |
Audit – Aging Management Programs |
03/30/15
04/13/15 |
03/30/15–04/03/15
04/13/15–04/17/15 |
Public Meeting – License Renewal Overview and Environmental Scoping meeting |
03/10/15 |
03/10/2015 |
Deadline for filing hearing requests and petitions for intervention |
04/06/15 |
04/06/15 |
Environmental scoping period ends |
04/06/15 |
04/06/15 |
Audit – Environmental |
05/04/15–05/07/15 |
05/05/15–05/07/15 |
Inspection – Regional |
09/2015 |
09/28/15 |
Issue safety evaluation report (SER) with open items |
02/2016 |
02/29/16 |
Issue draft supplemental environmental impact statement (SEIS) |
02/2016 |
02/08/16 |
U.S. Environmental Protection Agency FRN Published – availability of draft SEIS |
03/2016 |
02/19/16 |
Public Meeting – draft SEIS meeting |
03/22/16 |
03/22/16 |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting |
04/2016 |
04/19/16 |
End of draft SEIS comment period |
04/04/16 |
04/04/16 |
Issue final SER |
06/2016 |
06/02/16 |
ACRS full committee meeting |
07/2016 |
07/06/16 |
Issue final SEIS |
08/2016 |
08/26/16 |
U.S. Environmental Protection Agency FRN Published – availability of final SEIS |
09/2016 |
09/09/16 |
Decision – Director, NRR (no hearing) |
11/2016 |
10/19/16 |
Commission decision (if hearing is granted) |
TBD |
N/A |
Note: The LaSalle County Station, Units 1 and 2, review schedule was established and updated based on the letters below:

Safety Evaluation Report
The NRC staff reviewed the LaSalle County Station, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on February 29, 2016, as "Safety Evaluation Report with Open Items Related to the License Renewal of LaSalle County Station, Units 1 and 2." Upon further review and resolution of open items, the staff prepared a final report to document its findings. The document was issued on June 2, 2016, as "Final Safety Evaluation Report Related to the License Renewal of LaSalle County Station, Units 1 and 2," and subsequently published as NUREG-2205 in September 2016.
Environmental Impact Statements
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding LaSalle County Station, Units 1 and 2 (NUREG-1437, Supplement 57) Draft Report for Comment," was published in February 2016. This supplement documents the NRC staff's review of the environmental issues at the LaSalle County Station, Units 1 and 2 regarding the Exelon Generation Company, LLC., application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's recommendation regarding the proposed action.
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding LaSalle County Station, Units 1 and 2, (NUREG-1437, Supplement 57) Final Report," was published in August 2016. This supplement documents the NRC staff's review of the environmental issues at LaSalle County Station, Units 1 and 2, regarding the Exelon Generation Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's recommendation regarding the proposed action.

Public Involvement
The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date |
Description |
03/10/2015 |
Meeting to discuss the license renewal process and environmental scoping for LaSalle County Station, Units 1 and 2.
|
03/22/2016 |
Meeting to discuss the LaSalle County Station, Draft Supplemental Environmental Impact Statement.
|