This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

License Renewal Review Schedule*
These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones |
Scheduled |
Actual |
Receive Subsequent License RenewalApplication (SLRA) |
04/2025 |
04/01/2025 |
Publish Letter – SLRA Availability |
04/2025 |
04/08/2025 |
Publish Letter – Docketing Acceptance/Rejection and Opportunity for Hearing |
05/2025 |
04/28/2025 |
Publish Federal Register Notice FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping |
05/2025 |
05/22/2025 |
Environmental Scoping Period Ends |
06/2025 |
06/23/2025 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
07/2025 |
07/07/2025 |
Issue Draft Supplemental Environmental Impact Statement (SEIS) |
03/2026 |
|
Draft SEIS Comment Period Ends |
04/2026 |
|
Issue Safety Evaluation Report |
06/2026 |
|
Advisory Committee on Reactor Safeguards Full Committee Meeting |
07/2026 |
|
Issue Final SEIS |
08/2026 |
|
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS |
09/2026 |
|
Decision – Director, Office of Nuclear Reactor Regulation |
10/2026 |
|

Public Involvement
The public is encouraged to participate in the reactor license renewal processthrough public meetings, and public comment periods on rules, renewalguidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Project Managers
H.B. Robinson Steam Electric Plant, Unit 2 PMs |
License Renewal (Safety) |
Andrew Siwy |
License Renewal (Environmental) |
Karen Loomis |
Lead Power Plant |
Natreon Jordan |