The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

H.B. Robinson Steam Electric Plant, Unit 2 – Subsequent License Renewal Application

On this page

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

License Renewal Review Schedule*

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Scheduled Actual
Receive Subsequent License RenewalApplication (SLRA) 04/2025 04/01/2025
Publish Letter – SLRA Availability 04/2025 04/08/2025
Publish Letter – Docketing Acceptance/Rejection and Opportunity for Hearing 05/2025 04/28/2025
Publish Federal Register Notice FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 05/2025 05/22/2025
Environmental Scoping Period Ends 06/2025 06/23/2025
Deadline for Filing Hearing Requests and Petitions for Intervention 07/2025 07/07/2025
Issue Draft Supplemental Environmental Impact Statement (SEIS) 03/2026  
Draft SEIS Comment Period Ends 04/2026  
Issue Safety Evaluation Report 06/2026  
Advisory Committee on Reactor Safeguards Full Committee Meeting 07/2026  
Issue Final SEIS 08/2026  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 09/2026  
Decision – Director, Office of Nuclear Reactor Regulation 10/2026  

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal processthrough public meetings, and public comment periods on rules, renewalguidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date Description
TBD TBD

To top of page

Project Managers

H.B. Robinson Steam Electric Plant, Unit 2 PMs
License Renewal (Safety) Andrew Siwy
License Renewal (Environmental) Karen Loomis
Lead Power Plant Natreon Jordan

To top of page