License Renewal Review Schedule*

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones

Scheduled

Actual

Receive Subsequent License RenewalApplication (SLRA)

04/2025

04/01/2025

Publish Letter – SLRA Availability

04/2025

04/08/2025

Publish Letter – Docketing Acceptance/Rejection and Opportunity for Hearing

05/2025

04/28/2025

Publish Federal Register Notice FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping

05/2025

05/22/2025

Environmental Scoping Period Ends

06/2025

06/23/2025

Deadline for Filing Hearing Requests and Petitions for Intervention

07/2025

07/07/2025

Issue Draft Supplemental Environmental Impact Statement (SEIS)

12/2025

12/22/2025

Draft SEIS Comment Period Ends

01/2026

02/23/2026

Issue Final SEIS

03/2026

 

U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS

03/2026

 

Issue Safety Evaluation Report

04/2026

 

Decision – Director, Office of Nuclear Reactor Regulation

04/2026

 

To top of page

Environmental Review

NUREG-1437, Supplement 13, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Second Renewal, Regarding Subsequent License Renewal for H.B. Robinson Steam Electric Plant, Unit No. 2, Draft Report for Comment” was made publicly available on December 22, 2025. The draft supplemental environmental impact statement documents the NRC staff's review of the environmental impacts of license renewal for H.B. Robinson Steam Electric Plant, Unit 2. This draft supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action and the environmental impacts of alternatives to the proposed action. It also includes the staff's preliminary recommendation regarding the proposed action.

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal processthrough public meetings, and public comment periods on rules, renewalguidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date

Description

TBD

TBD

To top of page

Project Managers

H.B. Robinson Steam Electric Plant, Unit 2 PMs

License Renewal (Safety)

Mark Yoo

License Renewal (Environmental)

Karen Loomis

Lead Power Plant

Natreon Jordan

To top of page

Page Last Reviewed/Updated Friday, January 09, 2026

Page Last Reviewed/Updated Friday, January 09, 2026