Monticello Nuclear Generating Plant, Unit 1 – Subsequent License Renewal Application

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Note: The Monticello subsequent license renewal application (SLRA) is contained in ADAMS Package ML23009A352.

(To top of page)

License Renewal Review Schedule*

* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the listed PM for the latest information on meetings and status.

Milestones Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) January 2023 January 9, 2023
Publish Federal Register Notice (FRN) – SLRA Availability January 2023 January 31, 2023
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing February 2023 March 3, 2023
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping March 2023 March 10, 2023
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping March 2023 March 22, 2023
Environmental Scoping Period Ends April 2023 April 10, 2023
Deadline for Filing Hearing Requests and Petitions for Intervention May 2023 May 2, 2023
Issue Draft Supplemental Environmental Impact Statement (DSEIS) February 2024 --
Public Meeting – Draft SEIS Meeting, If Needed May 2024 --
End of DSEIS Comment Period April 2024 --
Issue Safety Evaluation Report March 2024 March 18, 2024 
Advisory Committee on Reactor Safeguards Full Committee Meeting May 2024 --
Issue Final SEIS October 2024 --
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS October 2024 --
Decision – Director, Office of Nuclear Reactor Regulation December 2024 --

(To top of page)

Safety Evaluation

The NRC staff reviewed the Monticello Nuclear Generating Plant, Unit 1, subsequent license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants" and prepared a safety evaluation to document its findings. The "Safety Evaluation to the SLRA of Monticello Nuclear Generating Plant, Unit 1" was issued on March 18, 2024.

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

(To top of page)

Project Managers for Monticello, Unit 1

Monticello Nuclear Generating Plant PMs
License Renewal (Safety) Marieliz Johnson
License Renewal (Environmental) Jessica Umana
Lead Power Plant Brent Ballard