Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

StandardReview Plan for the Review of Safety Analysis Reports for Nuclear Power Plants:LWR Edition — Steam and Power Conversion System (NUREG-0800,Chapter 10)

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Section Title Rev. Date Updated
10.2 Turbine Generator Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
10.2.3 Turbine Rotor Integrity Rev. 2 03/2007
Draft Rev. 2 06/1996
Rev. 1 07/1981
Rev. 0 11/1975
10.3 Main Steam Supply System Rev. 4 03/2007
Draft Rev. 4 06/1996
Rev. 3 04/1984
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
10.3.6 Steam and Feedwater System Materials Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
10.4.1 Main Condensers Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
10.4.2 Main Condenser Evacuation System Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 07/1978
Rev. 0 11/1975
10.4.3 Turbine Gland Sealing System Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 07/1978
Rev. 0 11/1975
10.4.4 Turbine Bypass System Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
10.4.5 Circulating Water System Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 03/1978
Rev. 0 11/1975
10.4.6 Condensate Cleanup System Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 03/1978
Rev. 0 11/1975
10.4.7 Condensate and Feedwater System Rev. 4 03/2007
Draft Rev. 4 06/1996
Rev. 3 04/1984
Rev. 2 07/1981
Rev. 1 03/1978
Rev. 0 11/1975
10.4.8 Steam Generator Blowdown System (PWR) Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 07/1978
Rev. 0 11/1975
10.4.9 Auxiliary Feedwater System (PWR) Rev. 3 03/2007
Draft Rev. 3 06/1996
Rev. 2 07/1981
Rev. 1 04/1978
Rev. 0 11/1975
  Branch Technical Positions (BTPs)    
BTP 10-1 Design Guidelines for Auxiliary Feedwater System Pump Drive and Power Supply Diversity for Pressurized Water Reactor Plants (Former Section 10.4.9 BTP has been separated into an individual section.) Rev. 3 03/2007
BTP 10-2 Design Guidelines for Avoiding Water Hammers in Steam Generators (Former Section 10.4.7 BTP has been separated into an individual section.) Rev. 4 03/2007