Public Meetings for 2002

This page lists, in chronological order, the notices, slides and summaries documenting the public meetings held concerning Reactor Vessel Head Degradation for 2002. To learn about future meetings, see our public meeting schedule page.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
12/23/2002

Category 1 meeting: Discuss the license's expansion of their System Health Assurance Plan

12/10/2002

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station

12/10/2002

Category 1 meeting: Discuss License performance and progress on the Return to Service Plan as part of the IMC 0350 Process

11/26/2002

Category 1 meeting: To Discuss the Davis-Besse Reactor Vessel Incore Monitoring Instrumentation Nozzles, Inspection, and Potential for Leakage

11/26/2002

Category 1 meeting: To Discuss the New Davis-Besse Containment Building Emergency Sump Design

11/20/2002

Lessons Learned Task Force Public Meeting

11/13/2002

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station.

11/13/2002

Category 1 meeting: Discuss License performance and progress on the Return to Service Plan as part of the IMC 0350 Process

10/16/2002

Category 1 meeting: Discuss preliminary findings and observations from the two NRC special inspections conducted to review radiolocial work planning, dose to workers during the outage, and offsite contamination events

10/16/2002

Category 1 meeting: Discuss licensee performance and progress on the Return to Service Plan as of the IMC 0350 Process.

10/16/2002

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station

09/18/2002

Category 1 meeting: Discuss the licensee's planned corrective actions to address the Davis-Besse organizational and human performance problems presented to the NRC during the August 15, 2002, public meeting.

09/17/2002

Category 3 meeting: Present to the local public the status of the NRC's oversight panel activities for the Davis-Besse Nuclear Power Station

09/17/2002

Category 1 meeting: Discuss licensee performance and progress on the Return to Service Plan as part of the IMC 0350 Process

08/23/2002

Category 2 meeting: This meeting is to discuss the NEI and PWR licensees Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles Inspections Programs."

08/20/2002

Category 3 meeting: Present to the local public the status of the NRC's oversight panel activities for the Davis-Besse Nuclear Power Station.

08/20/2002

Category 1 meeting: Discuss licensee performance and plans for restart as part of the IMC 0350 process.

08/15/2002

Category 1 meeting: Discuss the licensee's root cause analysis of the non-technical issues that led to the reactor pressure vessel head degradation.

07/24/2002

Category 2 meeting: Opportunity for industry to present to the NRC a revised generic inspection program for detection and control of leakage and corrosion in the reactor vessel head and penetration areas of pressurized water reactors.

07/16/2002

Category 1 meeting: Discuss licensee performance and plans for restart as part of the IMC 0350 Process

07/16/2002

Category 3 Meeting: Present to the local public the status of NRC's oversight panel activities for the Davis-Besse Nuclear Power Station

06/19/2002

Public Meeting: To discuss the NRC's Davis-Besse Reactor Vessel Head Degradation Lessons-Learned Task Force Charter, including objectives, scope, team composition, schedule, and review activities. This meeting is considered category 3 in accordance with NRC guidance on public meetings.

06/12/2002

Public Meeting: To discuss the NRC's Davis-Besse Reactor Vessel Head Degradation Lessons-Learned Task Force Charter, including objectives, scope, team composition, schedule, review activities, and activities to be conducted onsite at Davis-Besse.

06/12/2002

Public Meeting: To discuss plant performance and plans for restart of the Davis-Bese Nuclear Power Station, as part of the implementation of NRC's Inspection Manual Chapter (IMC) 0350.

06/12/2002

Public Meeting: Status of the NRC's activities related to the plant performance and plans for restart of the Davis-Besse Nuclear Power Station.

06/12/2002

American Nuclear Society 2002 Annual Meeting - Reactor Pressure Vessel Head Degradation

06/04/2002

Public Meeting: To discuss replacing the Davis-Besse reactor pressure vessel head

05/22/2002

NRC RES-MRP Alloy 600 Meeting Slides

05/20/2002

Public Meeting: To discuss the option of replacing the Davis-Besse reactor pressure vessel head.

Meeting has been postponed, date to be determined.

05/09/2002

Public Meeting: Implementation of NRC Oversight Panel (IMC 350)

05/07/2002

Public Meeting: Root Cause Analysis of the Degradation of the Davis-Besse Reactor Pressure Vessel Head

04/10/2002

Public Meeting: FirstEnergy Nuclear Operating Company updating Davis Besse Reactor Vessel Head Degradation condition and follow up actions

04/05/2002

NRC Public Meeting: To present, to the licensee, FirstEnergy Nuclear Operating Company, the results of NRC End-of-Cycle assessment

04/05/2002

NRC Public Meeting: to present, to the licensee, the NRC Augmented Inspection Team's preliminary findings regarding the loss of pressure boundary material from the Davis Besse reactor vessel head.

03/20/2002

Public Meeting: NRC updated to Stakeholders on Reactor Vessel Head Degradation program.

03/19/2002

Public Meeting: NEI/EPRI-MRP presentation to NRC staff updating Davis Besse Reactor Vessel Head Degradation condition and follow up actions

For related information see Generic Activities on Alloy 600 Cracking.