Approved Power Uprate Application Information For Surry 1 & 2

The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.

NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.

On this page:

Surry 1 & 2
Docket Nos. 50-280 & 50-281

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Application Information

Date Description Adams
Accession No.
01/27/2010 Surry Power Station Units 1 and 2 License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML100320264

To top of page

Supplement Information

Date Description Adams
Accession No.
02/04/2010 Supplemental Information Supporting License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML100480781
04/29/2010 Response to Request for Additional Information Regarding License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML101200269

To top of page

Amendment Information

Date Description Adams
Accession No.
09/24/2010 Issuance of Amendments Regarding Measurement Uncertainty Recapture Power Uprate ML101750002