Approved Power Uprate Application Information For North Anna 1 & 2
The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.
NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.
On this page:
North Anna 1 & 2
Docket Nos. 50-338 & 50-339
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Application Information
Date |
Description |
Adams
Accession No. |
03/26/2009 |
Virginia Electric and Power Company (Dominion) North Anna Power Station Units 1 and 2 License Amendment Request Measurement Uncertainty Recapture Power Uprate |
ML090900055 |
Supplement Information
Date |
Description |
Adams
Accession No. |
07/08/2009 |
Response to Request for Additional Information License Amendment Request Measurement Uncertainty Recapture Power Uprate |
ML091910204 |
07/16/2009 |
Response to Request for Additional Information License Amendment Request Measurement Uncertainty Recapture Power Uprate |
ML091970595 |
07/24/2009 |
Response to Request for Additional Information License Amendment Request Measurement Uncertainty Recapture Power Uprate |
ML092050714 |
Amendment Information
Date |
Description |
Adams
Accession No. |
10/22/2009 |
Issuance of Amendments Regarding Measurement Uncertainty Recapture Power Uprate (TAC Nos. ME0965 and ME0966) |
ML092250616 |