The Nuclear Regulatory Commission staff has established a special oversight panel to coordinate the agency's activities in assessing the performance problems associated with the corrosion damage to the reactor vessel head at the Davis-Besse Nuclear Power Plant, monitoring corrective actions, and evaluating the readiness of the plant to resume operations.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
12/23/02

Category 1 meeting: Discuss the license's expansion of their System Health Assurance Plan

12/10/02

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station

12/10/02

Category 1 meeting: Discuss License performance and progress on the Return to Service Plan as part of the IMC 0350 Process

11/20/02

Lessons Learned Task Force Public Meeting

11/13/02

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station.

11/13/02

Category 1 meeting: Discuss License performance and progress on the Return to Service Plan as part of the IMC 0350 Process

10/16/02

Category 1 meeting: Discuss preliminary findings and observations from the two NRC special inspections conducted to review radiolocial work planning, dose to workers during the outage, and offsite contamination events

10/16/02

Category 1 meeting: Discuss licensee performance and progress on the Return to Service Plan as of the IMC 0350 Process.

10/16/02

Category 3 meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station

09/18/02

Category 1 meeting: Discuss the licensee's planned corrective actions to address the Davis-Besse organizational and human performance problems presented to the NRC during the August 15, 2002, public meeting.

09/17/02

Category 3 meeting: Present to the local public the status of the NRC's oversight panel activities for the Davis-Besse Nuclear Power Station

09/17/02

Category 1 meeting: Discuss licensee performance and progress on the Return to Service Plan as part of the IMC 0350 Process

08/23/02

Category 2 meeting: This meeting is to discuss the NEI and PWR licensees Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles Inspections Programs."

08/20/02

Category 3 meeting: Present to the local public the status of the NRC's oversight panel activities for the Davis-Besse Nuclear Power Station.

08/20/02

Category 1 meeting: Discuss licensee performance and plans for restart as part of the IMC 0350 process.

08/16/02 Transmittal of NRC Inspection Manual Chapter 0350 Panel Restart Checklist
08/15/02

Category 1 meeting: Discuss the licensee's root cause analysis of the non-technical issues that led to the reactor pressure vessel head degradation.

07/16/02

Category 1 meeting: Discuss licensee performance and plans for restart as part of the IMC 0350 Process

07/16/02

Category 3 Meeting: Present to the local public the status of NRC's oversight panel activities for the Davis-Besse Nuclear Power Station

07/03/02 Davis Besse IMC 0350 Charter Revision 1
06/12/02

Public Meeting: To discuss plant performance and plans for restart of the Davis-Bese Nuclear Power Station, as part of the implementation of NRC's Inspection Manual Chapter (IMC) 0350.

06/12/02

Public Meeting: Status of the NRC's activities related to the plant performance and plans for restart of the Davis-Besse Nuclear Power Station.

05/09/02

Public Meeting: Implementation of NRC Oversight Panel (IMC 350)

05/03/02 NRC Press Release III-02-024: Davis-Besse Oversight Panel to Hold First Meeting May 9 in Oak Harbor, Ohio
04/30/02 NRC Press Release III-02-023: Establishes Agency Oversight Panel for Davis-Besse Reactor Head Degradation Issue
04/29/02 Letter from J.E. Dyer, Regional Administrator, Region III, to Howard Bergendahl, Vice President - Nuclear, Davis-Besse, regarding NRC Oversight Efforts regarding the Davis-Besse Nuclear Power Station
03/06/01 Inspection Manual Chapter 0350: Oversight of Operating Reactor Facilities in an Extended Shutdown as a Result of Significant Performance Problems.

For related information see Reactor Pressure Boundary Integrity Issues for Pressurized Water Reactors.