R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Application

Image of R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Application

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

  •  

(To top of page)

Subsequent License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the ;NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone

Scheduled

Actual

Receive Subsequent License Renewal Application (SLRA)

April-June 2026

 

Publish Federal Register Notice (FRN) – SLRA Availability

TBD

 

Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing

TBD

 

Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping

TBD

 

Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping

TBD

 

Environmental Scoping Period Ends

TBD

 

Deadline for Filing Hearing Requests and Petitions for Intervention

TBD

 

Issue Draft Supplemental Environmental Impact Statement (DSEIS)

TBD

 

End of DSEIS Comment Period

TBD

 

Issue Safety Evaluation Report

TBD

 

Issue Final SEIS

TBD

 

U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS

TBD

 

Decision – Director, Office of Nuclear Reactor Regulation

TBD

 

 

(To top of page)

Environmental Review

 

(To top of page)

Safety Evaluation

 

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date

Description

09/11/2025

Pre-application public meetings to discuss the license renewal process with Constellation Energy, LLC for the R.E. Ginna Nuclear Power Plant

(To top of page)

Project Managers

R.E. Ginna Nuclear Power Plant PMs

License Renewal (Safety)

Jessica Hammock

License Renewal (Environmental)

Angela Sabet

Lead Power Plant

V. Sreevinas

(To top of page)

Page Last Reviewed/Updated Thursday, September 18, 2025

Page Last Reviewed/Updated Thursday, September 18, 2025