Issued Early Site Permit - Vogtle Site
Southern Nuclear Operating Company (SNC) submitted an application for an early site permit (ESP) for the Vogtle site on August 15, 2006. On August 16, 2007, SNC submitted to the U. S. Nuclear Regulatory Commission (NRC) a supplement to its ESP application expanding the scope of the application to include a request for approval to perform selected construction activities, generally labeled limited work authorization (LWA). On August 26, 2009, the NRC issued the Vogtle site ESP and LWA. For detail (including Revision 5 of the application, the related review schedule, and the associated staff documentation), see the following topics on this page:
Application Information
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Review Schedule - Overall Project
Milestone |
Completion Date Actual - A
Target - T |
Receive early site permit application |
08/15/06 - A |
Press Release Announcing Receipt & Availability |
08/15/06 - A |
FRN published for receipt and availability |
08/29/06 - A |
Issue Applicant Letter of Acceptance of the Application for Docketing |
09/19/06 - A |
Press Release Announcing Notice of Acceptance for Docketing |
09/19/06 - A |
FRN Published Announcing Acceptance & Docketing |
09/26/06 - A |
FRN Published for Notice of Intent (Environmental Scoping Process) |
10/05/06 - A |
FRN Published for Notice of Hearing |
10/12/06 - A |
Press Release Announcing Notice of Hearing |
10/06/06 - A |
Inspection of Quality Assurance Program Implementation Complete |
10/05/06 - A |
Environmental Site Audit |
10/17/06 - A |
Environmental Scoping Meeting |
10/19/06 - A |
Deadline for Filing Petitions for Intervention & Contentions |
12/11/06 - A |
Scoping Period Ends |
12/04/06 - A |
Environmental Requests for Additional Information (RAIs) issued to applicant |
12/29/06 - A |
Applicant Submits Response to Environmental RAIs |
01/30/07 - A |
Safety and Emergency Planning (EP) RAIs Issued to the Applicant |
03/15/07 - A |
Applicant Submits Responses to Safety and EP RAIs |
04/16/07 - A |
Safety Evaluation Report (SER) issued W/OI |
08/30/07 - A |
Draft Environmental Impact Statement (EIS), Notice of Availability |
09/14/07 - A |
Public Meeting to Discuss Draft EIS |
10/04/07 - A |
Applicant Submits Responses to SER Open Items |
10/15/07 - A |
Initial ACRS Subcommittee Meeting on SER W/OI |
10/24/07 - A |
Initial ACRS Full Committee Meeting on SER W/OI |
11/01/07 - A |
ACRS Interim Letter to Commission |
11/20/07 - A |
End of Draft EIS Comment Period |
12/28/07 - A |
Advanced SER with no open items issued |
11/12/08 - A |
Post Advanced SER with no open items on NRC Public Website |
11/17/08 - A |
Final ACRS Subcommittee Meeting on Advanced SER with no open items |
12/03/08 - A |
Final ACRS Full Committee Meeting on Advanced SER with no open items |
12/04/08 - A |
ACRS Final Letter Report to the Commission |
12/22/08 - A |
Final EIS Issued |
08/22/08 - A |
Final SER Issued |
02/05/09 - A |
Contested Hearing on Environmental Issures |
03/16/09 -
03/19/09 - A |
Mandatory Hearing |
03/23/09 -
03/25/09 - A |
ASLB Initial Decision |
08/17/09 - A |
Issuance of the ESP and LWA |
08/26/09 - A |
Review Schedule - Limited Work Authorization Request
Milestone |
Completion Date Actual - A
Target - T |
Receipt of LWA Supplemental |
08/16/07 - A |
Issue Applicant Letter with Review Schedule |
09/12/07 - A |
Issue 1st Round Safety RAIs to Applicant |
10/26/07 - A |
Applicant Responds to 1st Round Safety RAIs |
11/28/07 - A |
Issue 2nd Round Safety RAIs to Applicant |
01/11/08 - A |
Applicant Responds to 2nd Round Safety RAIs |
02/13/08 - A |
Isssue 3rd Round Safety RAIs to Applicant |
07/21/08 - A |
Applicant Responds to 3rd Round Safety RAIs |
08/14/08 - A
08/21/08 - A |
Final Safety Evaluation Report for an ESP and LWA at the Vogtle Electric Generating Plant Site
The NRC issued the Final Safety Evaluation Report for the Vogtle ESP application on February 5, 2009
NUREG-1923, containing the safety evaluation report for the VEGP ESP Application, was issued August 2009
Final Environmental Impact Statement
See NUREG-1872,"Final Environmental Impact Statement for an Early Site Permit (ESP) at the Vogtle Electric Generating Plant Site." (August 2008)
See Errata to NUREG-1872, " Final Environmental Impact Statement for an Early Site Permit (ESP) at the Vogtle Electric Generating Plant Site." (August 2008) (Errata)
Vogtle Early Site Permit
On August 26, 2009, the NRC issued the Vogtle Electric Generating Plant ESP for a site located approximately 26 miles southeast of Augusta, Georgia.
For additional information regarding the Vogtle site ESP and LWA, please Contact a Public Affairs Officer.