Issued Early Site Permit - Clinton Site
Exelon Generation Company submitted its application for an early site permit (ESP) for the Clinton site on September 25, 2003, and the U.S. Nuclear Regulatory Commission (NRC) issued the Exelon ESP on March 15, 2007. For detail, see the following topics on this page:
Application Information
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Review Schedule
Milestone |
Completion Date Actual - A
Target - T |
Receive early site permit application |
09/25/03 - A |
Press Release announcing receipt and availability |
10/15/03 - A |
Federal Register notice (FRN) published for receipt and availability |
10/24/03 - A |
FRN published announcing acceptance |
10/30/03 - A |
FRN published for Notice of Intent (environmental scoping process) |
11/25/03 - A |
Press Release announcing acceptance and notice of hearing |
12/08/03 - A |
FRN published for mandatory hearing |
12/12/03 - A |
Environmental scoping meeting |
12/18/03 - A |
Scoping period ends |
01/09/04 - A |
Deadline for filing petitions for intervention |
01/12/04 - A |
1st inspection complete |
01/16/04 - A |
Deadline for submitting contentions |
05/03/04 - A |
Environmental requests for additional information (RAIs) issued to applicant |
05/11/04 - A |
Applicant submits response to environmental RAIs |
07/23/04 - A |
Safety and emergency planning (EP) RAIs issued to the applicant |
07/27/04 - A |
Applicant submits responses to safety and EP RAIs |
10/12/04 - A |
Draft safety evaluation report (SER) issued |
02/10/05 - A |
Draft environmental impact statement (EIS) to EPA, Issue Notice of Availability |
03/02/05 - A |
Public meeting to discuss draft EIS |
04/19/05 - A |
Applicant submits responses to SER open items |
04/26/05 - A |
2nd inspection complete |
05/19/05 - A |
End of draft EIS comment period |
05/25/05 - A |
Optional final inspection complete |
N/A1 |
Regional Administrator's Letter |
N/A1 |
Supplemental draft SER issued |
08/26/05 - A |
ACRS subcommittee meeting on draft SER |
09/07/05 - A |
ACRS full committee meeting on draft SER |
09/08/05 - A |
ACRS interim letter to Commission |
09/22/05 - A |
Applicant submits responses to supplemental draft SER open items |
10/31/05 - A |
Applicant submits the final ESP application revision |
01/10/06 - A |
Final SER issued |
02/17/06 - A |
ACRS subcommittee meeting on final SER |
03/08/06 - A |
ACRS full committee meeting on final SER |
03/09/06 - A |
ACRS letter to Commission |
03/24/06 - A |
Final SER issued as NUREG |
05/01/06 - A |
Final EIS issued to EPA/Issue Notice of Availability |
07/20/06 - A |
Atomic Safety and Licensing Board (ASLB) initial decision |
12/28/06 - A |
Commission decision to approve issuance of Exelon ESP |
03/08/07 - A |
Permit Issued |
03/15/07 - A |
1 "Optional final inspection and regional administrator's letter not needed."
Safety Evaluation Report
See NUREG-1844 "Safety Evaluation Report for an Early Site Permit (ESP) at the Exelon Generation Company, LLC (EGC) ESP Site."
Environmental Impact Statement
See NUREG-1815, "Environmental Impact Statement for an Early Site Permit (ESP) at the Exelon ESP Site."
Exelon Early Site Permit
On March 15, 2007, the NRC issued the Exelon ESP for a site located approximately 6 miles east of the city of Clinton in central Illinois.
For additional information regarding the Exelon ESP, please Contact a Public Affairs Officer.