NRC Action Number(s) and
Facility Name |
Action Type
(Severity) &
Civil Penalty
(if any) |
Date
Issued |
Description |
EA-20-043
EA-20-150
Turkey Point Nuclear Generating Station, Unit Nos. 3 and 4 |
NOVCP
(SLIII)
$150,000 |
04/06/2021 |
On April 6, 2021, the NRC issued a Notice of Violation and Proposed Imposition of a Civil Penalty in the amount of $150,000 to the Florida Power & Light Company for a Severity Level III problem at Turkey Point Nuclear Generating Station. The enforcement action is the result of two separate investigations completed by the NRC’s Office of Investigations. The first investigation determined that three mechanics willfully falsified the inspection and maintenance of a safety-related check valve in the auxiliary feedwater system. This event occurred in January 2019. The second investigation determined that two technicians, a supervisor and a manager, willfully failed to inform control room staff that maintenance had been performed on the wrong unit’s Chemical and Volume Control System charging pump. This second event occurred in July 2019. As a result of these two investigations, the staff identified two violations of 10 CFR 50.9(a), “Completeness and Accuracy of Information,” and a violation of 10 CFR 50, Appendix B, Criterion XVII, “Quality Assurance Records.” |
EA-16-099
Turkey Point 3 & 4 |
NOV
(SL III) |
10/10/2016 |
On October 10, 2016, the NRC issued a Notice of Violation to Florida Power & Light for a Severity Level III violation involving Turkey Point Nuclear Plant's failure to maintain complete and accurate records as required by 10 CFR 50.9(a). Specifically, on multiple occasions between November 2014 and April 2015, Fire Watch Shift Supervisors initialed and signed hourly fire watch logs indicating that hourly fire watches had been completed, with all required areas checked, when on multiple occasions some areas had not been checked or hourly fire watches had not been performed at all. |
EA-12-001
Turkey Point 3 & 4 |
NOV
(White)
NOVCP
(SL III)
$140,000 |
04/09/2012 |
On April 9, 2012, the NRC issued a Notice of Violation associated with a White Significance Determination Process (SDP) finding and a Severity Level III violation with a Proposed Imposition of Civil Penalty in the amount of $140,000 to Florida Power and Light Company (FPL). The White Finding was issued for the failure of Turkey Point personnel to maintain the effectiveness of their emergency plan, as required by 10 CFR 50.54(q) and 10 CFR 50.47(b), and the Severity Level III violation and Civil Penalty were issued for FPL’s failure to make an eight hour report, as required by 10 CFR 50.72(b)(3)(xiii). Specifically, from December 4, 2010, to July 13, 2011, and from October 10 to October 28, 2011, FPL failed to follow and maintain the effectiveness of its emergency plan when portions of the Technical Support Center (TSC) ventilation system were removed from service for maintenance, without compensatory measures. FPL failed to report this condition as required from December 4, 2010, to July 13, 2011. |
EA-10-037
Turkey Point 3 |
NOV
(White)
NOVCP
(SL III)
$70,000 |
06/21/2010 |
On June 21, 2010, the NRC issued a White finding with two associated violations to Florida Power and Light Company (FP&L) as a result of inspections at Turkey Point Nuclear Plant Unit 3. This White finding involves the licensee's failure to adequately address degradation of Boraflex, a fixed neutron absorber material used in the Turkey Point Unit 3 spent fuel pool. Boraflex degradation resulted in a reduction in the Boron-10 areal density of the spent fuel storage racks such that, when considering the biases and uncertainties identified in Chapter 9 of the Updated Final Safety Analysis Report, the effective neutron multiplication factor would not have been maintained less than 1.0 if the spent fuel pool had been flooded with unborated water. The NRC identified that FP&L had violated 10 CFR 50, Appendix B, Criterion XVI, "Corrective Action," which requires that conditions adverse to quality be promptly identified and corrected, and Technical Specification 5.5.1.1.a, which requires that the spent fuel storage racks be maintained with an effective neutron multiplication factor less than 1.0 if flooded with unborated water, when considering the biases and uncertainties described in the Updated Final Safety Analysis Report. The NRC also issued FP&L a Severity Level III Notice of Violation with a proposed $70,000 civil penalty for failure to comply with 10 CFR 50.73, which requires, in part, that licensees report any condition prohibited by the plant's Technical Specifications. As discussed, Boraflex degradation led to a condition prohibited by Turkey Point Unit 3 Technical Specifications, but this condition was not reported to the NRC as required by 10 CFR 50.73. |
EA-07-110, 07-113,
07-116, 07-119
Turkey Point 3 & 4 |
ORDER |
01/22/2008 |
On January 22, 2008, a Notice of Violation and Proposed Imposition of Civil Penalty in the amount of $208,000 was issued was issued for a Severity Level II problem consisting of (1) the licensees failure to ensure, on or about April of 2004, that each of its armed responders was equipped with a contingency weapon in accordance with an NRC Order issued on February 25, 2002, Section B.4(f); (2) the licensees failure to ensure, on or about August 2005, that each of its armed responders was equipped with a contingency weapon in accordance with the licensee Physical Security Plan; (3) a violation of 10 CFR 50.9, incomplete and inaccurate information; and (4) the failure of the licensee to make a one hour report to the NRC as required in 10 CFR 73, Appendix G, Paragraph 1.l(a)(3). |
EA-06-200
Turkey Point 3 |
NOV
(White) |
11/22/2006 |
On November 22, 2006, a Notice of Violation was issued for a violation associated with a WHITE significance determination process finding involving the failure to adequately assess and manage the increase in risk of performing maintenance on the A-train 480-volt 3C load center while the facility was operating in decay heat removal mode with one operating A-train residual heat removal (RHR) pump. The violation was cited against 10 CFR Part 50.65(a)(4) for failure to adequately assess and manage the increase in risk before performing maintenance on the A-train 480-volt 3C load center. |
EA-06-027
Turkey Point 3 & 4 |
NOV
(White) |
04/17/2006 |
On April 17, 2006, a Notice of Violation was issued for a violation associated with a White SDP finding involving the licensee's failure to restore the B auxiliary feedwater (AFW) pump to operable status within 30 days, to place the unit in at least Hot Standby during this time, and to identify and correct the condition adverse to quality even though pump bearing vibration levels and oil samples provided indication of the adverse condition. In this case, the B AFW pump was placed in service on September 10, 2003, in an inoperable condition due to a misaligned radial bearing, and the inoperable condition was not identified until November 7, 2005. The Notice of Violation cited the licensee's failure to implement the requirements in Technical Specification 3.7.1.2 and 10 CFR Part 50, Appendix B, Criterion XVI. |
EA-00-230
Turkey Point 3 & 4 |
NOV
(SL III) |
06/06/03 |
On June 5, 2003, a Notice of Violation was issued for a Severity Level III violation for discriminating against an employee at the Turkey Point Nuclear Plant for engaging in protected activity. |
EA-96-051
Turkey Point 3 & 4 |
NOVCP
(SL III)
$100,000 |
07/16/96 |
Discrimination against an individual when he was fired for engaging in protected activities. |