The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Correspondence Related to NRC Bulletin 2003-02

On August 21, 2003, NRC issued Bulletin 2003-02, "Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity." There are two types of responses to this bulletin: initial and 60-day. The initial response is for the request for information about the licensees’ lower head penetration inspection program, and the 60-day response is for the request for summary of the lower head penetration inspections. The initial response is due within 30 days of the bulletin for licensees with a refueling outage prior to December 31, 2003, and within 90 days of the bulletin for other licensees. The 60-day response is due within 60 days of plant restart.

On November 5, 2003, the NRC issued Temporary Instruction 2515/152, Revision 1 , which revises the area on reporting requirements.

Region I Region II Region III Region IV

On this page:

 

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

 

Region 1

Plant Name Initial Response 60 Day Response Related Documents
Beaver Valley 1 Initial Response 60 Day Response 08/29/05 Closeout Letter
Beaver Valley 2 Initial Response 60 Day Response 10/18/04 Closeout Letter
Ginna Initial Response 60 Day Response 11/08/04 Closeout Letter
Indian Point 2 Initial Response 60 Day Response 08/02/05 Closeout Letter
Indian Point 3 Initial Response 60 Day Response 08/30/05 Closeout Letter
Millstone 3 Initial Response 60 Day Response 11/09/04 Closeout Letter
Salem 1 Initial Response 60 Day Response 12/06/04 Closeout Letter
Salem 2 Initial Response 60 Day Response 12/06/04 Closeout Letter
Seabrook 1 Initial Response 60 Day Response 02/09/05 Closeout Letter
Three Mile Island 1 Initial Response 60 Day Response 02/03/05 Closeout Letter

To top of page

Region 2

Plant Name Initial Response 60 Day Response Related Documents
Catawba 1 Initial Response 60 Day Response 01/13/05 Closeout Letter
Catawba 2 Initial Response 60 Day Response 07/19/05 Closeout Letter
Crystal River 3 Initial Response 60 Day Response

01/18/05 Closeout Letter

Crystal River was permanently shut down on February 20, 2013

Farley 1 Initial Response 60 Day Response 09/01/05 Closeout Letter
Farley 2 Initial Response 60 Day Response 02/03/05 Closeout Letter
McGuire 1 Initial Response 60 Day Response 01/04/04 Closeout Letter
McGuire 2 Initial Response 60 Day Response 01/04/04 Closeout Letter
North Anna 1 Initial Response 60 Day Response 02/25/05 Closeout Letter
North Anna 2 Initial Response 60 Day Response 09/23/04 Closeout Letter
Oconee 1 Initial Response 60 Day Response 01/06/05 Closeout Letter
Oconee 2 Initial Response 60 Day Response 01/06/05 Closeout Letter
Oconee 3 Initial Response 60 Day Response 03/07/05 Closeout Letter
Robinson 2 Initial Response 60 Day Response 03/03/05 Closeout Letter
Sequoyah 1 Initial Response 60 Day Response 09/30/05 Closeout Letter
Sequoyah 2 Initial Response 60 Day Response 10/06/04 Closeout Letter
Shearon Harris 1 Initial Response 60 Day Response 08/01/05 Closeout Letter
Summer Initial Response 60 Day Response 02/04/05 Closeout Letter
Surry 1 Initial Response 60 Day Response 08/01/05 Closeout Letter
Surry 2 Initial Response 60 Day Response 09/22/04 Closeout Letter
Turkey Point 3 Initial Response 60 Day Response 04/22/05 Closeout Letter
Turkey Point 4 Initial Response 60 Day Response 04/22/05 Closeout Letter
Vogtle 1 Initial Response 60 Day Response 01/13/05 Closeout Letter
Vogtle 2 Initial Response 60 Day Response 01/13/05 Closeout Letter
Watts Bar 1 Initial Response 60 Day Response 10/06/04 Closeout Letter

To top of page

Region 3

Plant Name Initial Response 60 Day Response Related Documents
Braidwood 1 Initial Response 60 Day Response 04/08/05 Closeout Letter
Braidwood 2 Initial Response 60 Day Response 01/31/05 Closeout Letter
Byron 1 Initial Response 60 Day Response 02/02/05 Closeout Letter
Byron 2 Initial Response 60 Day Response 02/02/05 Closeout Letter
Davis Besse Initial Response 60 Day Response 01/24/06 Closeout Letter
DC Cook 1 Initial Response 60 Day Response 10/15/04 Closeout Letter
DC Cook 2 Initial Response 60 Day Response 07/28/05 Closeout Letter
Kewaunee Initial Response 60 Day Response

06/28/05 Closeout Letter

Kewaunee Power Station was permanently shut down on May 7, 2013

Point Beach 1 Initial Response 60 Day Response 11/22/04 Closeout Letter
Point Beach 2 Initial Response 60 Day Response 11/22/04 Closeout Letter
Prairie Island 1 Initial Response 60 Day Response 07/07/05 Closeout Letter
Prairie Island 2 Initial Response 60 Day Response 10/05/04 Closeout Letter

To top of page

Region 4

Plant Name Initial Response 60 Day Response Related Documents
Arkansas Nuclear 1 Initial Response 60 Day Response 01/14/05 Closeout Letter
Callaway Initial Response 60 Day Response 12/07/04 Closeout Letter
Comanche Peak 1 Initial Response 60 Day Response 12/02/04 Closeout Letter
Comanche Peak 2 Initial Response 60 Day Response 12/02/04 Closeout Letter
Diablo Canyon 1 Initial Response 60 Day Response 04/05/05 Closeout Letter
Diablo Canyon 2 Initial Response 60 Day Response 09/14/05 Closeout Letter
Palo Verde 1 Initial Response 60 Day Response 10/03/05 Closeout Letter
Palo Verde 2 Initial Response 60 Day Response 10/03/05 Closeout Letter
Palo Verde 3 Initial Response 60 Day Response 10/03/05 Closeout Letter
South Texas 1 Initial Response 60 Day Response 09/07/05 Closeout Letter
South Texas 2 Initial Response 60 Day Response 04/04/05 Closeout Letter
Wolf Creek 1 Initial Response 60 Day Response 01/20/05 Closeout Letter

To top of page

Page Last Reviewed/Updated Tuesday, November 24, 2020