Date |
Description |
06/24/14 |
Palo Verde, Unit 3, Licensee Event Report (LER) supplement 50-530/3013-001-01 |
11/20/13 |
Palo Verde, Unit 3, NRC staff's request for additional information and the licensee's response to NRC staff's request for additional information on the bottom mounted instrumentation repair |
11/08/13 |
Palo Verde, Unit 3 Relief Request 51, requesting use of an alternative to ASME Code, Section XI allowing half-nozzle repair on the Bottom Mounted Instrumentation |
10/06/13 |
Palo Verde, Unit 3 Bottom Mounted Instrumentation Leakage event occurred |
10/15/03 |
Supplement to LER 03-003, Bottom Mounted Instrumentation Penetration Indications |
09/08/03 |
NRC Special Inspection Team Report 050000498/2003008 and 05000499/2003008 and Exercise of Enforcement Discretion |
08/21/03 |
June 12, 2003 Telecon Summary |
08/21/03 |
June 19, 2003 Telecon Summary |
08/21/03 |
Bulletin 2003-02: Leakage from Reactor Pressure Vessel Lower Head penetrations and Reactor Coolant Pressure Boundary Integrity |
08/18/03 |
STP Unit 1 Reactor Pressure Vessel Head Inspection Results |
08/15/03 |
NRC Approval - Request for Relief, RR-ENG-2-32, From ASME Code Requirements for Approval of Half-Nozzle Repair/Replacement for BMI Penetrations |
08/13/03 |
NRC Information Notice 2003-11: Leakage Found on Bottom Mounted Instrumentation Nozzles |
08/08/03 |
Staff observation/assessment of half-nozzle repair design calculations |
08/08/03 |
July 10, 2003 Telecon Summary |
08/08/03 |
June 26, 2003 Telecon Summary |
08/08/03 |
May 22, 2003 Telecon Summary |
08/01/03 |
Request for Relief, RR-ENG-2-35, From the Requirements of the ASME Boiler and Pressure Vessel Code Concerning Use of an Electro-Discharge Machining (EDM) Process (TAC NO. MB9655) |
08/01/03 |
Relief Request RR-ENG-2-33, Alternative Flaw Characterization Criteria for Two Bottom-Mounted Instrument Penetration Welds (TAC NO. MB9727) |
07/31/03 |
NRC Special Inspection Team Review and NRC Staff Evaluation of South Texas Project, Unit 1, Reactor Pressure Vessel Bottom-Mounted Instrumentation Penetration Leakage Investigation and Repair Activities |
07/31/03 |
Summary of Exit Meeting for Special Inspection of Bottom Mounted Instrumentation Nozzle Leakage in South Texas Project, Unit (NRC Inspection Report 050000498/2003008) |
07/30/03 |
Request for Withholding Information from Public Disclosure Per Section 2.790 of Title 10 of the Code of Federal Regulations Concerning Bottom Mounted Instrumentation Forced Outage (TAC No. MB8435) |
07/23/03 |
Revised Summary of ASME Code Calculations Performed for Repair of Bottom Mounted Instrumentation Penetrations |
07/17/03 |
Supplemental Response to Request for Additional Information Regarding Request for Alternative RR-ENG-2-32 (TAC No. MB9696) |
07/17/03 |
Confirmation of 7/11 letter Updated Commitments to Investigate and Repair Bottom Mounted Instrumentation Penetration Indications |
07/15/03 |
May 29, 2003 Telecon Summary |
07/15/03 |
May 20, 2003 Telecon Summary |
07/11/03 |
Updated Commitment to Investigate and Repair Bottom Mounted Instrumentation Penetration Indications. |
07/03/03 |
Response to Request for Additional Information Regarding Request for Alternative RR-ENG-2-32 (TAC No. MB9696) |
07/02/03 |
South Texas Project Unit 1 Docket No. STN 50498 Summary of ASME Code Calculations Performed for Repair of Bottom Mounted Instrumentation Penetrations |
07/01/03 |
Revised Response to Request for Additional Information Regarding Request for Alternatives RR-ENG-2-35 |
06/27/03 |
NRC Approval - Request for Relief, RR-EING-2-30, Revision 2, From ASME Code Requirements for Approval of ASME Section XI Code Case N-516-2 for Underwater Welding of Core Barrel Locking Tab |
06/26/03 |
Response to Request for Additional Information Regarding Request for Alternatives RR-ENG-2-35 |
06/25/03 |
NRC Approval - Request for Relief, RR-ENG-2-31, From ASME Code Requirements for Approval of ASME Section XI Code Cases N-2143-1 and 2143-1 for the Second 10-Year Inspection Interval |
06/25/03 |
Request for Relief from ASME Section XI Requirements Associated with Characterizing Flaws in Bottom Mounted Instrumentation Penetration Welds (Relief Request RR-ENG-2-33) |
06/19/03 |
Request for Alternative to ASME Section XI Requirements Associated with Half-Nozzle Repair/Replacement for Bottom Mounted Instrument Penetrations (Relief Request RR-ENG-2-32) |
06/17/03 |
May 15, 2003 Telecon Summary |
06/17/03 |
May 8, 2003 Telecon Summary |
06/13/03 |
Request for Alternatives to ASME Section XI Requirements Associated with Mechanical Processing of Thermally cut Surfaces (Relief Request RR-ENG-2-35) |
06/11/03 |
Licensee Event Report 03-003, Bottom Mounted Instrumentation Penetration Indications |
06/10/03 |
Relief Request RR-ENG-30, Rev. 2 |
06/02/03 |
Revised Request for Approval of ASME Section XI Code Case N-516-2 for Underwater Welding of Core Barrel Locking Tab (Relief Request RR-ENG-2-30) |
06/02/03 |
Bottom Mounted Instrumentation Forced Outage Confidential Information |
05/28/03 |
NRC Press Release 03-069 - NRC to Hold Public Meeting June 5 on Reactor Vessel Penetration Leakage at South Texas Project |
05/27/03 |
April 17, 2003 - Telephone Conversation Summary |
05/23/03 |
April 22, 2003 - Telephone Conversation Summary |
05/22/03 |
South Texas Press Release - STP releases preliminary inspection results |
05/20/03 |
Morning Report for May 20, 2003 |
05/15/03 |
Request for Approval of ASME Section IX Code Cases 2142-1 and 2143-1 for the Second Ten-Year Inspection Interval (Relief Request RR-ENG-2-31) |
05/12/03 |
Responses to NRC Questions regarding Bottom Mounted Instrumentation Penetration Indications |
05/08/03 |
Request for Approval of ASME Section XI Code Case N-516-2 for the Second Ten-Year Inservice Inspection Interval (Relief Request RR-ENG-2-30) |
05/08/03 |
April 24, 2003 - Telephone Conversation Summary |
05/05/03 |
NRC Press Release IV-03-021 - NRC to Conduct Special Inspection at South Texas Project Unit 1 |
05/05/03 |
Charter for the NRC Special Inspection Team at South Texas Project - Review of Licensee Actions Related to Reactor Vessel Bottom Mounted Instrumentation Penetration Leakage |
04/28/03 |
NRC Press Release 03-051: NRC to hold Public Meeting May 1 on Reactor Vessel Penetration Leakage at South Texas Project |
04/24/03 |
Commitment to Investigate and Repair Bottom Mounted Instrumentation Penetration Indications |
04/18/03 |
NRC Preliminary Notification PNO-IV-03-022: Reactor Vessel Bottom Head Penetration Leakage |
04/14/03 |
NRC Event Report 39754 |
02/13/03 |
Response to RAI on Bulletin 2002-01 |
11/25/02 |
Bulletin 2002-01 RAI Letter |
09/11/02 |
30 Day Response to Bulletin 2002-02 |
05/16/02 |
60 Day Response to Bulletin 2002-01 |
04/02/02 |
15 Day Response to Bulletin 2002-01 |
03/18/02 |
NRC Bulletin 2002-01: Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity |
08/29/01 |
15 Day Response to Bulletin 2001-01 |
03/09/89 |
South Texas Response to GL 88-05 |
05/31/88 |
South Texas Response to GL 88-05 |