2008 QA Inspection and Audit Reports
The purpose of inspection and audit reports is to document the inspection/audit scope, observation, and findings of inspections and audits conducted by the NRC. The NRC performs inspections and audits to oversee the commercial nuclear industry to determine whether its requirements are being met by licensees and applicants, and their contractors. The following early site permit and combined license (COL) application inspections, and Pre-Design Certification and Pre-COL audits have been conducted:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date |
Description |
12/24/08 |
Westinghouse AP1000 Design Certification Amendment Application - Inspection of the implementation of the quality assurance and Part 21 programs governing the amendment to the AP1000 Design Certification the Westinghouse facility in Monroeville, PA.
|
03/25/08 |
Calvert Cliffs, audit of the Calvert Cliffs combined license application (COLA) Part 2 development program at the Constellation Energy facility in Baltimore, Maryland. |
03/19/08 |
Bellefonte Combined License Application - Inspection of the implementation of the quality assurance program governing the simulated open channel hydraulics model at the TVA facility in Chattanooga, TN.
- Applicant Responses 1 | 2
|
02/15/08 |
Shearon Harris, audit of the Shearon Harris combined license application (COLA) development program at the Progress Energy facility in Raliegh, North Carolina.
|
01/23/08 |
Mitsubishi Heavy Industries, LTD., audit of the US Advanced Pressurized Water Reactor US-APWR) Design Certification (DC) application development program and completeness review at the National Conference Center in Lansdowne, Virginia.
|