Erosion/Corrosion-Induced Pipe Wall Thinning (Generic Letter 89-08)
May 2, 1989
TO: ALL HOLDERS OF OPERATING LICENSES OR CONSTRUCTION PERMITS FOR
NUCLEAR POWER PLANTS
SUBJECT: EROSION/CORROSION-INDUCED PIPE WALL THINNING
(GENERIC LETTER 89 - 08)
Pursuant to 10 CFR 50.54(f), the U.S. Nuclear Regulatory Commission (NRC) is
requiring information to assess safe operation of reactors when erosion/
corrosion significantly degrades piping and components of high-energy carbon
steel piping systems. The principal concern is whether the affected plants
continue to meet their licensing basis when erosion/corrosion degrades the
pressure boundary to below the applicable code design value.
Main feedwater systems, as well as other power conversion systems, are
important to safe operation. Failures in these systems of active components
such as valves or pumps or of passive components such as piping can result in
undesir-able challenges to plant safety systems required for safe shutdown and
accident mitigation. Failure of high-energy piping, such as feedwater system
piping, can result in complex challenges to operating staff and the plant
because of potential system interactions of high-energy steam and water with
other systems, such as electrical distribution, fire protection, and security.
All licensees have committed to adhere to criteria, codes and standards for
high-energy piping systems described in licensing documents. Such commitments
are a part of the licensing basis for the facility. An important part of this
commitment is that piping will be maintained within allowable thickness
values.
Our concerns regarding this issue were prompted by incidents at Surry Unit 2
and the Trojan plant. The Surry incident occurred on December 6, 1986, and it
was caused by catastrophic failure of feedwater piping. The Trojan incident
was discovered in June 1987, which was the first time that pipe wall thinning
led to piping replacement in the safety-related portion of the feedwater
lines. In addition to these two cases, incidents of pipe wall thinning or
rupture because of erosion or erosion/corrosion have been reported at many
other nuclear power plants. In many of these cases, the licensees had
inspected the two-phase lines for some years, but it was not until the Surry
incident that they started to examine some single-phase lines. Many licensees
discovered pipe wall thinning in the single-phase lines. Some of the reported
incidents are listed below:
1. A pipe rupture at Haddam Neck occurred in March 1985. The pipe ruptured
downstream of a normal level control valve for a feedwater heater. The
actual rupture was approximately 1/2 inch by 2 1/4 inches, and the failure
was caused by flow impingement. The eroded section of pipe was replaced.
In addition, corresponding pipes of similar systems were examined.
2. A catastrophic pipe rupture at Surry Unit 2 occurred in December 1986.
The break was located in an elbow in the 18-inch line about 1 foot from
the 24-inch header. A 2- by 4-foot section of the wall of the suction
8905040276
.Generic Letter 89-08 -2- May 2, 1989
line to the A main feedwater pump was blown out. Investigation of the
accident and examination of data by the licensee, NRC, and others led to
the conclusion that failure of the piping was caused by erosion/corrosion
of the carbon steel pipe wall.
3. During the June 1987 outage at the Trojan Nuclear Plant, it was
discovered that at least two areas of the straight sections of the main
feedwater piping system had experienced wall thinning to an extent that
the pipe wall thickness would have reached the minimum thickness required
by the design code (ANSI B31.7, "Nuclear Power Piping") during the next
refueling cycle. These areas are in safety-related portions of the ASME
Class 2 piping inside the containment. In addition, numerous piping
components of the nonsafety-related portions of the feedwater lines were
also found to have suffered extensive wall thinning.
4. During the September 1988 outage, the licensee for Surry Unit 2
discovered that pipe wall thinning had occurred more rapidly than
expected. On the suction side of one of the main feedwater pumps, an
elbow installed during the 1987 refueling outage lost 20 percent of its
0.500-inch wall in 1.2 years. In addition, wall thinning is continuing
in safety-related main feedwater piping and in other nonsafety-related
condensate piping. The exact cause of the accelerated wall thinning is
still under investigation by both the licensee and the NRC.
In light of the above experiences, the NRC issued six information notices
(86-106 and Supplements 1, 2, and 3; 87-36, and 88-17) and Bulletin 87-01
addressing this problem. The staff review of licensees' responses to the
bulletin indicates that the pipe wall thinning problem is widespread for
single-phase and two-phase high-energy carbon steel systems. The systems and
components reported as having experienced pipe wall thinning are listed in
Section 6 of the attachment to this letter. The staff review also showed that
wall thinning in single phase feedwater-condensate systems is more prevalent
among pressurized-water reactors (PWRs) but also occurs in boiling-water
reactors (BWRs).
The staff audited 10 operating plants (7 PWRs and 3 BWRs) in late 1988 to
assess implementation of erosion/corrosion monitoring programs by licensees
and to ensure that adequate guidance was provided for corrective actions and
other activities regarding repair and replacement of degraded piping and
components. Detailed audit findings are described in Section 7 of NUREG-1344,
which is enclosed with this letter. In general, all licensees have developed
and put in place an erosion/corrosion monitoring program that meets the intent
of NUMARC guidelines (Appendix A of NUREG-1344). In addition, all licensees
have completed their initial examination as recommended by NUMARC. However,
the staff found that none of these licensees has implemented formalized
procedures or adminis-trative controls to ensure continued long-term
implementation of its erosion/ corrosion monitoring program for piping and
components within the licensing basis. Therefore, you should provide
assurances that a program, consisting of systematic measures to ensure that
erosion/corrosion does not lead to degra-dation of single phase and two phase
high-energy carbon steel systems has been implemented. The detailed
information should not be submitted for NRC review.
.Generic Letter 89-08 -3- May 2, 1989
Additional insight into the phenomena related to erosion/corrosion of carbon
steel components is provided in the enclosure to this letter (NUREG-1344).
You are required to submit your response, signed under oath or affirmation, as
specified in 10 CFR 50.54(f), within 60 days of receipt of this letter. Your
response will be used to determine whether your license should be modified,
suspended, or revoked. Your response should include information on whether or
not you have implemented or intend to implement a long term erosion/corrosion
monitoring program that provides assurances that procedures or administrative
controls are in place to assure that the NUMARC program or another equally
effective program is implemented and the structural integrity of all high-
energy (two phase as well as single phase) carbon steel systems is maintained.
If this program is not yet implemented you should include the scheduled imple-
mentation date.
This request is covered by the Office of Management and Budget Clearance Number
3150-0011, which expires December 31, 1989. The estimated average burden is
200 man-hours per addressee response, including assessing the actions to be
taken, preparing the necessary plans, and preparing the response. This
estimated average burden pertains only to these identified response-related
matters and does not include the time for actual implementation of the
recommended actions.
Send comments regarding this burden estimate or any other aspect of this col-
lection of information, including suggestions for reducing this burden, to
the Records and Reports Management Branch, Division of Information Support
Services, Office of Information Resources Management, U.S. Nuclear Regulatory
Commission, Washington, D.C. 20555; and to the Paperwork Reduction Project
(3150-0011), Office of Management and Budget, Washington, D.C. 20503.
Sincerely,
James G. Partlow
Associate Director for Projects
Office of Nuclear Reactor Regulation
Enclosures:
1. NUREG-1344
2. Listing of Recently Issued Generic Letters
Page Last Reviewed/Updated Tuesday, March 09, 2021