Recombiner Capability Requirements of 10 CFR 50.44 (c)(3)(ii) (Generic Letter No. 84-09)
UNITED STATES
NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555
May 8, 1984
ALL LICENSEES OF OPERATING REACTORS
Gentlemen:
SUBJECT: RECOMBINER CAPABILITY REQUIREMENTS OF 10 CFR 50.44 (c)(3)(ii)
(GENERIC LETTER NO. 84-09)
On December 2, 1981, the NRC amended SS50.44 of its regulations by addition
of the provisions in SS50.44(c)(3). One of these provisions requires
licensees of those light water reactors (both BWRs and PWRs) that rely upon
purge/repressurization systems as the primary means of hydrogen control to
provide a recombiner capability by the end of the first scheduled outage
after July 5, 1982, of sufficient duration to permit the required
modifications. Those plants for which notices of hearing on applications for
construction permits were published on or after November 5, 1970 are rot
permitted by 10 CFR 50.44(e) to rely on purge/repressurization systems as
the primary means for hydrogen control. Therefore, these plants are not
affected by the requirement for recombiner capability; the licensees of
these plants are being furnished a copy of this generic letter for
information only.
After adoption of the ar.ended rule, and as a result of the new inerting
requirement in SS50.44(c)(3), the BWR Mark I Owners Group (incorporating
studies performed by Northeast Nuclear Energy Company) undertook a
substantial program to demonstrate that the Mark I plants potentially
affected by the recombiner capability requirements of the rule do not need
to rely on use of the safety grade purge/repressurization system required by
the original 10 CFR 50.44 rule as the primary means of hydrogen control.
Extensive review and independent studies by the NRC staff supported the
findings of the Mark I Owners Group program. (This letter does not address
PWRs because the inerting requirement of SS50.44(c)(3) does not apply to
PWRs and, therefore, the licensees of PWRs are not likely to be able to make
a comparable demonstration.)
The Commission has determined that a Mark I BWR plant will be found to not
rely upon purge/repressurization systems as the primary means of hydrogen
control if certain technical criteria are satisfied. To avoid any
misunderstanding, we wish to make clear that a plant that has a "safety
grade" purge/repressurization system designed to conform with the general
requirements of Criteria 41, 42 and 43 of Appendix A of 10 CFR Part 50 and
installed in accordance with SS50.44(f) or SS50.44(g) must continue to have
that system, even though it may be determined with respect to ss50.44(c)(3)
that the plant does not rely on that system as the primary means for
hydrogen control; thus, a decision on recombiner capability does not affect
the requirements of SS50.44(f) and SS50.44(g) for the "safety grade" purge/
repressurization system.
8405080316
.
- 2 -
For those inerted Mark I BWR containments (for which notices on the
construction permits were published before November 5, 1970) that do not
rely upon safety grade purge/repressurization systems as the primary means
of hydrogen control, the Commission determination, cited above, is
applicable Provided the following criteria are met:
1) The plant has technical specifications (limiting conditions for
operation) requiring that. when the containment is required to be
inerted the containment atmosphere be less than four percent oxygen,
and
2) The plant has only nitrogen or recycled containment atmosphere for use
in all pneumatic control systems within containment, and
3) There are no potential sources of oxygen in containment other than that
resulting from radiolysis of the reactor coolant. Consideration of po-
tential sources of inleakage of air and oxygen into containment should
include consideration of not only normal plant operating conditions but
also postulated loss-of-coolant-accident conditions. These potential
sources of inleakage should include instrument air systems, service air
systems. MSIV leakage control systems purge lines, penetrations
pressurized with air &nd inflatable door seals.
Accordingly, any Mark I BWR owner which has concluded that a recombiner
capability is not required for its facility is requested to submit a
response to this letter within 45 days. Each submittal should indicate the
applicability of the generic studies submitted by the Mark I Owners Group to
the licensee's facility and include additional information relative to the
three criteria cited above to enable the staff to make a comparable
decision.
This request for information was approved by the Office of Management and
Budget under clearance number 3150-0011 which expires April 30, 1985.
Comments on burden and duplication my be directed to the Office of
Management and Budget, Reports Management Room 3208, New Executive Office
Building, Washington, D. C. 20503.
Sincerely,
Darrell G. Eisenhut, Director
Division of Licensing
Office of Nuclear Reactor Regulation
.
Page Last Reviewed/Updated Tuesday, March 09, 2021