Followup Actions Resulting from the NRC Staff Reviews Regarding The Three Mile Island Unit 2 Accident (Generic Letter 79-40)
GL79040
UNITED STATES
NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555
(TO ALL OPERATING NUCLEAR POWER PLANTS)
Gentlemen:
SUBJECT: FOLLOWUP ACTIONS RESULTING FROM THE NRC STAFF REVIEWS REGARDING
THE THREE MILE ISLAND UNIT 2 ACCIDENT
Over the past several months following the Three Mile Island accident, the
NRC staff has been conducting an intensive review of the design and
operational aspects of nuclear power plants and the emergency procedures for
coping with potential accidents. The purpose of these efforts was to
identify measures that should be taken in the short-term to reduce the
likelihood of such accidents and to improve the emergency preparedness in
responding to such events. To carry out this review, efforts within NRR were
established in four areas: (a) licensee emergency preparedness, (b) operator
licensing, (c) bulletins and orders followup (primarily in the areas of
auxiliary feedwater system reliability; loss of feedwater and small break
loss-of-coolant accident analysis; emergency operating guidelines and
procedures) and (d) Short-Tern Lessons Learned.
It is the purpose of this letter to set forth NRR's requirements established
to date as a result of those efforts. Additional requirements may be
developed as NRR's Lessons Learned Task Force completes its Long-Term
Requirements. In addition, Commission review of the results of other
investigations, including the Presidential Commission and the NRC's Special
Inquiry Group, can be expected to load to additional requirements.
Lessons Learned Task Force Report
The principal element of the staff activities listed above is contained
in the report titled, "TMI-2 Lessons Learned Task Force Status Report
and Short-Term Recommendations" (NUREG-0578), a copy of which was
previously sent to you. The Task Force report contains a set of
recommendations to be implemented in two stages over the next 16 months
on operating plants. The Task Force recommended 20 licensing
requirements and three rulemaking matters in 12 broad areas.
The Advisory Committee on Reactor Safeguards has completed its review
of the Task Force report. The several public meetings of the ACRS
subcommittee on TMI-2 and the public meeting of the full committee
.
- 2 -
on August 9 provided an opportunity for the presentation and discussion
of public comments on the report. The ACRS letter of August 13, 1979 to
Chairman Hendrie states that the Committee agrees with the intent and
substance of all the Task Force recommendations, except four upon which
the Committee offered constructive comments to achieve the same
objectives articulated by the Task Force. The Committee also noted
that effective implementation will require a more flexible, perhaps
extended, schedule than proposed by the Task Force. A copy of the ACRS
letter is provided as Enclosure 1.
After considering all comments received, we have concluded that the
following actions are appropriate for operating nuclear power plants.
(a) The staff will be proposing a new rule on a Limiting Condition of
Operation to require plant shutdown for certain human or
procedural errors, particularly those which are repetitive in
nature. As such, no action is required on your part at this time.
(b) At the present time we are delaying efforts regarding proposed
rulemaking on both the inerting requirements for Mark l and II BWR
containments, and the requirement regarding hydrogen recombiner
capability; accordingly, no action is required on your part at
this time.
(c) The ACRS comments on the shift technical advisor have resulted In
our reassessment of the possible means of achieving the two
functions which the Task Force intended to provide by this
requirement. The two functions are accident assessment and
operating experience assessment by people onsite with engineering
competence and certain other characteristics. We have concluded
that the shift technical advisor concept is the preferable
short-term method of supplying these functions. We have also
concluded that some flexibility in implementation may yield the
desired results if there is management innovation by individual
licensees. We have prepared a statement of functional
characteristics for the shift technical advisor that will be used
by the staff in the review of any alternatives proposed by
licensees. A copy is provided as Enclosure 2.
(d) Three additional instrumentation requirements for short-term
action were developed during the ACRS review of NUREG-0578. These
items relate to containment pressure, containment water
.
- 3 -
level and containment hydrogen monitors designed to follow the
course of an accident. Descriptions of these items are provided in
Enclosure 3.
(e) An additional requirement following issuance of NUREG-0578, which
concerned a remotely operable high point vent for gas from the
reactor coolant system, was developed. A description of this
requirement is provided in Enclosure 4.
(f) The Lessons Learned Task Force has compiled a set of errata and
clarifying comments for NUREG-0578. It Is provided as Enclosure 5.
Following our review of each of the proposed Task Force requirements,
ACRS review, and comments received we have concluded that all operating
reactor licensees should begin to implement the actions contained in
NUREG-0578, as modified and/or supplemented by items (a) through (f)
above, as soon as possible. Accordingly, please submit within 30 days
of receipt of this letter, your commitment to meet these requirements
on the implementation schedule contained in Enclosure 6. The
implementation dates for the Commission rulemaking actions a those
deferred actions, identified above, will be established later.
Regarding implementation of these topics for Systematic Evaluation
Program (SEP) plants that are part of the SEP, we have determined that
implementation of these topics should not, in general, wait for final
resolution of the SEP. For good cause shown, such as interaction with
an SEP topic resolution, implementation delay may be justifiable on a
selected issue.
Other Review Areas
Enclosure 7 outlines the requirements developed to date resulting from
the staff's Emergency Preparedness Studies. Enclosure 8 provides the
implementation schedules for the emergency preparedness requirements
which, you will note, includes three of the Lessons Learned Topics. We
also require that you provide commitments to comply with each of the
requirements of Enclosure 7 in accordance with the implementation
schedules shown in Enclosure 8. Such commitments should be included in
your letter due in 30 days of receipt of this letter. Further, the
Commission has initiated a rulemaking procedure, now scheduled for
completion in January 1980 in the area of Emergency Planning and
Preparedness. Additional requirements are to be expected when
rulemaking is completed and some modifications to the emergency
preparedness requirements contained in this letter may be necessary.
.
- 4 -
Enclosure 9 outlines the staff recommendations concerning improvements
in the area of operator training and are provided for your information.
Those recommendations are undergoing Commission review, and are
expected to be adopted as requirements in the near future. Further
Commission review in the areas of operator training and qualification
can be expected to result in substantial additional requirements.
A number of other related actions on your facility have been underway
for some time under the direction of the NRR Bulletins and Orders Task
Group. Each licensee will receive additional guidance from this group,
particularly related to auxiliary feedwater systems and small break
LOCAs, in the near future. Your activities should continue in these
areas, as all the mentioned activities are meant to complement one
another.
The measures discussed above represent a set of requirements that should be
implemented at this time. As stated earlier, other requirements may follow
in the future. To assist in explaining in more detail each of these
requirements, the NRC will hold regional meetings during the week of
September 24, 1979, similar to those held for Emergency Preparedness.
Attached as Enclosure 10 is s copy of the Federal Register Notice announcing
such meetings.
If you have any questions regarding these actions, please contact the NRC
Project Manager for your facility.
Sincerely,
Darrell G. Eisenhut, Acting Director
Division of Operating Reactors
Enclosures:
1. ACRS Ltr: Carbon to Hendrie dtd 8/31 /79
2. Alternatives to Shift Technical Advisor
3. Instrumentation to Monitor Containment conditions
4. Installation of Remotely Operated High Point Vents
in the Reactor Coolant System
5. NUREG-0578 Errata
6. Implementation Schedule
7. Requirements for Improving Emergency Preparedness
8. Emergency Preparedness Improvements - Implementation Schedule
9. Improvements in Operator Training
10. Federal Register Notice
Page Last Reviewed/Updated Tuesday, March 09, 2021