Application Review Schedule for the Combined License Application for Turkey Point, Units 6 and 7
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Florida Power and Light Company (FPL) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Turkey Point, Units 6 and 7.
Key Milestones |
Completion Date
Actual - A
Target - T |
Application Tendered |
06/30/09 - A |
Acceptance Review |
Acceptance Review Start
|
06/30/09 - A |
Docketing Decision Letter Issued/Acceptance Review Complete
|
09/04/09 - A |
Review Schedule Established/Schedule Letter Issued to Applicant
|
10/27/15 - A |
Safety Review |
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
|
06/16/15 - A |
Phase B - Advance Final safety evaluation report (SER) without Open Items
|
07/14/16 - A |
Phase C - ACRS Review of Advance Final SER
|
08/19/16 - A |
Phase D - Final SER
|
11/10/16 - A |
Environmental Review |
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
|
12/10 - A |
Phase 2 - Draft EIS issued to EPA
|
02/27/15 - A |
Phase 3 - Final EIS issued to EPA
|
10/28/16 - A |
Supplement to Final EIS issued
|
12/02/16 - A |
Hearing |
Commission or ASLB hold mandatory hearing
|
Schedule Under
Review |
License |
Commission decision on issuance of COL application
|
|
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.