On June 30, 2009, Florida Power & Light Company (FPL) submitted its application for combined licenses (COLs) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs) designated as Turkey Point, Units 6 and 7.
For detail (including the latest submittal of the application, the related review schedule, and the associated staff documentation), see the following topics on this page:
Reference Documents
In accordance with Title 10, Part 52, of the Code of Federal Regulations (10 CFR Part 52), "Licenses, Certifications, and Approvals for Nuclear Power Plants," a COL application may reference a standard design certification, an early site permit, both, or neither. Many COL applications have referenced an application for design certification, in accordance with 10 CFR 52.55(c). On that basis, FPL referenced Westinghouse's application to amend the AP1000 standard design certification and cited the following amended design control document (DCD) in its COL original application for Turkey Point, Units 6 & 7:

Application Information
The following table provides access to the COL Application that FPL submitted for Turkey Point, Units 6 & 7.
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Final Safety Analysis Report and associated Technical/Topical Reports would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
* A "roadmap" providing a discussion of the Revision 8 changes to the application was provided in a Florida Power and Light Company letter dated September 16, 2016.

Review Schedule
Key Milestones |
Completion Date
Actual - A
Target - T |
Application Tendered |
06/30/09 - A |
Acceptance Review |
Acceptance Review Start
|
06/30/09 - A |
Docketing Decision Letter Issued/Acceptance Review Complete
|
09/04/09 - A |
Review Schedule Established/Schedule Letter Issued to Applicant
|
10/27/15 - A |
Safety Review |
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
|
06/16/15 - A |
Phase B - Advance Final safety evaluation report (SER) without Open Items
|
07/14/16 - A |
Phase C - ACRS Review of Advance Final SER
|
08/19/16 - A |
Phase D - Final SER
|
11/10/16 - A |
Environmental Review |
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
|
12/10 - A |
Phase 2 - Draft EIS issued to EPA
|
02/27/15 - A |
Phase 3 - Final EIS issued to EPA
|
10/28/16 - A |
Supplement to Final EIS issued
|
12/02/16 - A |
Hearing |
ASLB holds evidentiary hearing
|
05/02 - 03/17 - A |
Commission holds mandatory hearing
|
12/12/17 - A |
License |
Commission decision on issuance of COL application
|
04/05/18 - A |

Safety Evaluations
This section lists the Safety Evaluations that the NRC has issued in connection with its review of the COL application that FPL submitted for Turkey Point, Units 6 & 7.

Environmental Impact Statement
This section lists the Environmental Impact Statement that the NRC has issued in review of the COL application that FPL submitted for Turkey Point, Units 6 & 7.

Topical Reports
The NRC has issued no Topical Reports in connection with its review of the COL application that FPL submitted for Turkey Point, Units 6 & 7.

Combined Licenses (COLs)
This section provides the COLs that the NRC issued on April 12, 2018, in connection with its review of the COL application for Turkey Point, Units 6 and 7.

Summary Record of Decision
This section provides the Summary Record of Decision that the NRC issued in connection with its review of the COL application for Turkey Point, Units 6 and 7.


Contacts for the Turkey Point COL Application |
Safety Project Manager |
|
Environmental Project Manager |
Alicia Williamson |
Contact a Public Affairs Officer |