Licensing Schedule for the Mixed Oxide Fuel Fabrication Facility

The schedule in the following table is subject to change. It is based on the assumption that the Shaw AREVA MOX Services (MOX Services) application meets all applicable regulations.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Action
12/19/2000 The applicant submitted an Environmental Report (ER) to NRC
02/28/2001 The applicant submitted a request to NRC to construct a Mixed Oxide Fuel Fabrication Facility (MFFF) on the DOE's Savannah River Site.
04/18/2001 NRC published a notice in the Federal Register announcing that the NRC had accepted an application for authority to construct a MFFF.
01/31/2005 NRC issued the Final Environmental Impact Statement (NUREG-1767)
03/30/2005 NRC issued the Construction Authorization
03/31/2005 NRC issued the Final Safety Evaluation Report on the Construction Authorization Request for the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site, SC (NUREG-1821)
09/27/2006
11/16/2006
MOX Services submits the License Application and the Integrated Safety Analysis Summary to possess and use radioactive material
12/20/2006 NRC accepts license submittal for docketing
04/12/2007 Public meeting in Aiken, SC to discuss NRC's role, responsibilities, and the licensing process; inspection and enforcement; and public participation related to the review of the License Application for the MFFF
12/20/2010 NRC staff to complete review of the license application and the ISA Summary and prepare Safety Evaluation.