Location: Louisa, VA (40 miles NW of Richmond, VA); Region II; Type: Westinghouse Three-Loop; Licensed MWt: 2940
Location: Louisa, VA (40 miles NW of Richmond, VA); Region II; Type: Westinghouse Three-Loop; Licensed MWt: 2568
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 3, 2013 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technica...
Dominion Nuclear North Ann2, LLC , Dominioni5000 Dominion Boulevard, Glen Allen. VA 23060November 3, 2003Hon. J. W. Wall, Jr., Chairman ESP-0038Allendale County Council526 Memorial Ave.P.O. Box 190Allendale, SC 29810In the Matter ofDominion Nuclear North Anna, LLCNRC Docket No...
1PMNorthAnna3COLPEmails ResourceFrom: Jessie, JanelleSent: Friday, January 15, 2010 1:40 PMTo: Regina BorshSubject: RE: North Anna RAI 14.3.10-1 (EP ITAAC)ok-thanks yes, I will be there. See you next week Janelle From: Regina Borsh [mailto:regina.borsh@dom.com] Sent: Fri...
1NorthAnnaRAIsPEm ResourceFrom: Buckberg, PerrySent: Friday, November 21, 2014 11:01 AMTo: 'na3raidommailbox@dom.com' (na3raidommailbox@dom.com) (na3raidommailbox@dom.com)Cc: NorthAnnaRAIsPEm Resource; Weisman, Robert; Carpentier, Marcia; Giacinto, Joseph; Rivera-Varona, AidaS...
1PMNorthAnna3COLPEmails ResourceFrom: Ward, Jeffrey A [ja.ward@pnl.gov]Sent: Wednesday, September 02, 2009 11:45 AMTo: Williamson, Alicia; Sandusky, William F IIICc: ^PNNL NRC North Anna COL; NorthAnna3COL ResourceSubject: Re: Potential RAIs: North Anna Unit 3 - Rev. 2 ERGood...
1PMNorthAnna3COLPEmails ResourceFrom: Patel, ChanduSent: Thursday, February 02, 2012 3:39 PMTo: 'na3raidommailbox@dom.com'Cc: Weisman, Robert; Takacs, Michael; Johnson, JudySubject: Draft RAI 6282, FSAR Section 13.6, North Anna 3 COLAAttachments: Draft RAI 6282.docHi All, Ple...
1NorthAnnaRAIsPEm ResourceFrom: Buckberg, PerrySent: Thursday, October 16, 2014 8:13 AMTo: 'na3raidommailbox@dom.com' (na3raidommailbox@dom.com) (na3raidommailbox@dom.com)Cc: Patel, Chandu; NorthAnnaRAIsPEm Resource; Hinson, Charles; McCoppin, MichaelSubject: Draft North Anna ...
1PMNorthAnna3COLPEmails ResourceFrom: Alicia WilliamsonSent: Friday, February 29, 2008 5:31 PMTo: 'William F III Sandusky'Cc: Laura Quinn; 'Adam J Davis'Subject: Re: North Anna TravelBill We have reserved a block of rooms at the Hampton Inn-Fredericksburg for the upcoming Nort...
1PMNorthAnna3COLPEmails ResourceFrom: Christopher CookSent: Wednesday, May 21, 2008 6:35 PMTo: Andrea Johnson; Thomas KevernSubject: North Anna Hydrology Safety Audit Trip ReportAttachments: NA_Hydrology_SafetyAudit_TripReport.pdf; FW: Conference Details (MAY 22, 2008--04:30 P...
North Anna/ENV44/Oil SpillCertified Mail Return Receipt Requested December 6, 2000 Mr. Larry M. Carpenter DEQ - Valley Regional Office 4411 Early Road P. 0. Box 3000 Harrisonburg, Virginia 22801 RE: North Anna Power Station - Oil Release Dear Mr. Carpenter: The following infor...
1PMNorthAnna3COLPEmails ResourceFrom: Harry Ruth [HC.RUTH@LOUISA.NET]Sent: Sunday, April 13, 2008 12:32 PMTo: Francis Cameron; Thomas Hipschman; Christopher Cook; Michael Masnik; Alicia WilliamsonCc: Lake Anna Observer Attn: Ed Kube; Irene Luck (Central Virginian); Greg Doraz...
1NorthAnnaRAIsPEm ResourceFrom: Patel, ChanduSent: Wednesday, March 23, 2011 9:36 AMTo: 'na3raidommailbox@dom.com'Cc: Weisman, Robert; NorthAnnaRAIsPEm Resource; Scarbrough, Thomas; Kallan, PaulSubject: RAI Letter No. 62, RAI 5547, Section 3.11, North Anna 3 COLAAttachments: F...
1PMNorthAnna3COLPEmails ResourceFrom: Alicia WilliamsonSent: Monday, January 12, 2009 2:34 PMTo: elirons@deq.virginia.govCc: Sandusky, William F III; Marcia Carpentier; Michael Masnik; William Burton; NorthAnna3COL Resource; Jack CushingSubject: Request: North Anna Draft SEIS...
1PMNorthAnna3COLPEmails ResourceFrom: Kevern, ThomasSent: Wednesday, December 02, 2009 9:21 AMTo: NorthAnna3COL ResourceSubject: FW: North Anna COLA - safety review schedule From: Kevern, Thomas Sent: Wednesday, December 02, 2009 8:38 AM To: Joe Hegner; Regina.Borsh@dom.com...
Lake Anna 2007 Background/stocking/regulations Lake Anna is a 9,600-acre impoundment owned by the Dominion Virginia Power Company (Dominion). The reservoir spans Louisa, Spotsylvania and Orange counties a...
1PMNorthAnna3COLPEmails ResourceFrom: Alicia WilliamsonSent: Friday, March 14, 2008 11:30 AMTo: tony.banks@dom.comCc: Sandusky, William F III; Laura QuinnSubject: North Anna Site Audit Information Needs Hi Tony Attached is the North Anna site audit info needs list. I am expec...
1PMNorthAnna3COLPEmails ResourceFrom: Andrea JohnsonSent: Monday, March 02, 2009 9:50 AMTo: 'Regina.Borsh@dom.com'Cc: Thomas Kevern; NorthAnna3COL ResourceSubject: RE: Draft RAIs - - North Anna Unit 3 COLA Just to clarify regarding the Healthy Physics RAIs, more may be coming ...
1NorthAnnaRAIsPEm ResourceFrom: Buckberg, PerrySent: Friday, March 27, 2015 7:56 AMTo: ''na3raidommailbox@dom.com' (na3raidommailbox@dom.com) (na3raidommailbox@dom.com)'Cc: NorthAnnaRAIsPEm Resource; Shea, James; Karas, Rebecca; Graizer, Vladimir; Munson, CliffordSubject: Draf...
1PMNorthAnna3COLPEmails ResourceFrom: Patel, ChanduSent: Tuesday, June 03, 2014 2:26 PMTo: 'na3raidommailbox@dom.com' (na3raidommailbox@dom.com)Cc: PMNorthAnna3COLPEmails Resource; Weisman, Robert; Carpentier, Marcia; Buckberg, Perry; Nolan, RyanSubject: Draft RAI 7533, FSAR S...
1PMNorthAnna3COLPEmails ResourceFrom: Steve Tracton [s.tracton@hotmail.com]Sent: Tuesday, March 15, 2011 5:44 PMTo: Harry Ruth; skmarsala@deq.virginia.gov; Dozier, Tamsen; elirons@de.virginia.govCc: willie@buck.com; lcbs_jd@louisa.org; walterjoseph@hughes.net; twolakelovers@ya...
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technical...
North Anna COLA RAI status and SER with Open Items update 4/22/09 Note 1: This list only includes FSAR chapters 1, 2.5, 4, 6, 7, 8, 10, 11, 12, 15, 16, 17, 18 & 19 Note 2: FSAR chapters 4, 7 and 18 did not have RAIs issued Chapter/Title Question # (RAI letter) eRAI ID RAI Sta...
1PMNorthAnna3COLPEmails ResourceFrom: Christopher CookSent: Monday, July 14, 2008 9:26 AMTo: Alicia WilliamsonSubject: RE: North Anna Site Audit Open ItemsAttachments: Site Audit_Open Items-AW comments.docAlicia, What's the status on these? Where all the Discipline=Hydrology i...
14-1 14.0 INITIAL TEST PROGRAM This chapter of the combined license (COL) Final Safety Analysis Report (FSAR) addresses information concerning the initial test program (ITP) for structures, systems, and components (SSCs) and design features for both the nuclear portion...
1NorthAnnaRAIsPEm ResourceFrom: Patel, ChanduSent: Thursday, February 16, 2012 4:30 PMTo: 'na3raidommailbox@dom.com'Cc: NorthAnnaRAIsPEm Resource; Weisman, Robert; Takacs, Michael; Johnson, JudySubject: RAI Letter No. 95, RAI 6282, Section 13.6, North Anna 3 COLAAttachments: R...