Kewaunee
Initiating Events
Mitigating Systems
Significance: Feb 21, 2002
Identified By: NRC
Item Type: NCV NonCited Violation
Failure to Perform Thorough 10 CFR 50.59 Safety Evaluation
The inspectors identified a Non-Cited Violation for failure to perform an adequa...
October 23, 2003
EA-03-038
[Insert Addressee and Address (enclosure 3)]
SUBJECT: [INSERT FACILITY NAME] - REPLY TO RESPONSE TO ORDER FOR
FITNESS-FOR-DUTY ENHANCEMENTS FOR NUCLEAR SECURITY FORCE
PERSONNEL
Dear Mr. [Insert name]:
On April 29, 2003, the Nuclear Regulatory Co...
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
+ + + + +
BRIEFING ON OFFICE OF NUCLEAR SECURITY AND INCIDENT
RESPONSE (NSIR) PROGRAMS, PERFORMANCE AND PLANS
...
OFFICE OF ENFORCEMENT
ANNUAL REPORT
Fiscal Year 2001
U.S. Nuclear Regulatory Commission
OE Annual Report
- CONTENTS -
Contents ................................................. i
Abstract ............................................... v
Introduction & Overview ..........
July 30, 2003
Mr. Fred Dacimo
Site Vice President
Entergy Nuclear Northeast
Indian Point Nuclear Generating Station
295 Broadway, Suite 1
Post Office Box 249
Buchanan, NY 10511-0249
SUBJECT: INDIAN POINT 2 - NRC INTEGRATED INSPECTION REPORT
050000247/2003007
Dear Mr. Daci...
February 15, 2001
Mr. R. P. Powers
Senior Vice President
Nuclear Generation Group
American Electric Power Company
500 Circle Drive
Buchanan, MI 49107-1395
SUBJECT: D. C. COOK NUCLEAR POWER PLANT - NRC INSPECTION
REPORT 50-315/01-03(DRP); 50-316/01-03(DRP)
Dear Mr. Powers:
...
March 26, 2004
Florida Power and Light Company
ATTN: Mr. J. A. Stall, Senior Vice President
Nuclear and Chief Nuclear Officer
P.O. Box 14000
Juno Beach, FL 33408-0420
SUBJECT: TURKEY POINT NUCLEAR PLANT - NRC TRIENNIAL FIRE PROTECTION
INSPECTION REPORT 05000250/2...
1
NEAL R. GROSS
COURT REPORTERS AND TRANSCRIBERS
1323 RHODE ISLAND AVE., N.W.
(202) 234-4433 WASHINGTON, D.C. 20005-3701 (202) 234-4433
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
+ + + + +
31st ANNUAL REGULATORY INFORMATION CONFERENCE
+ + + ...
September 24, 2005
Southern Nuclear Operating Company, Inc.
ATTN: Mr. L. M. Stinson
Vice President - Farley Project
P. O. Box 1295
Birmingham, AL 35201-1295
SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT - NRC PROBLEM IDENTIFICATION
AND RESOLUTION INSPECTION REPORT 05000348/2005...
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
+ + + + +
BRIEFING ON NUCLEAR SECURITY
AND INCIDENT RESPONSE PROGRAMS
+ + + + +
ROCKVILLE, MARYLAND
+ + + + +
TUESDAY, MARCH 29, 2005
+ + + + +
The Commission met in open session at 9:30 a.m., at the
Nucle...
July 24, 2001
EA-01-173
Garry L. Randolph, Senior Vice
President and Chief Nuclear Officer
Union Electric Company
P.O. Box 620
Fulton, Missouri 65251
SUBJECT: CALLAWAY--NRC INSPECTION REPORT 50-483/01-03
Dear Mr. Randolph:
On July 7, 2001, the NRC completed an in...
November 14, 2005
George A. Williams, Site Vice President
Grand Gulf Nuclear Station
Entergy Operations, Inc.
P.O. Box 756
Port Gibson, MS 39150
SUBJECT: GRAND GULF NUCLEAR STATION - NRC INTEGRATED INSPECTION
REPORT 05000416/2005004
Dear Mr. Williams:
On September...
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
+ + + + +
BRIEFING ON STATUS OF OIS PROGRAMS,
PERFORMANCE, AND PLANS,
+ + + + +
ROCKVILLE, MARYLAND
+ + + + +
TUESDAY, FEBRUARY 22, 2005
+ + + + +
The Commission met in open session at 9:30 a.m., at the
N...
January 24, 2003
Mr. Bryce L. Shriver
Senior Vice President and
Chief Nuclear Officer
PPL Susquehanna, LLC
769 Salem Blvd., NUCSB3
Berwick, PA 18603-0467
SUBJECT: SUSQUEHANNA STEAM ELECTRIC STATION - NRC INTEGRATED
INSPECTION REPORT 50-387/02-06, 50-388/02-06
Dear Mr. S...
May 4, 2004
Garry L. Randolph, Senior Vice
President and Chief Nuclear Officer
Union Electric Company
P.O. Box 620
Fulton, MO 65251
SUBJECT: CALLAWAY PLANT - NRC INTEGRATED INSPECTION
REPORT 05000483/2004002
Dear Mr. Randolph:
On March 24, 2004, the NRC completed...
May 5, 2003
Virginia Electric and Power Company
ATTN.: Mr. David A. Christian
Sr. Vice President and
Chief Nuclear Officer
Innsbrook Technical Center - 2SW
5000 Dominion Boulevard
Glen Allen, VA 23060-6711
SUBJECT: NORTH ANNA POWER STATION - NRC INTEGRATED INSPECTION
REPO...
January 31, 2003
Mr. John L. Skolds, President
Exelon Nuclear
Exelon Generation Company, LLC
Quad Cities Nuclear Power Station
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: QUAD CITIES NUCLEAR POWER STATION
NRC INTEGRATED INSPECTION REPORT 50-254/03-02; 50-265/03-02
D...
January • February • March • April • May • June • July • August • September • October • November • DecemberThis page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.De...
July 18, 2003
South Carolina Electric & Gas Company
ATTN: Mr. Stephen A. Byrne
Senior Vice President, Nuclear Operations
Virgil C. Summer Nuclear Station
P. O. Box 88
Jenkinsville, SC 29065
SUBJECT: VIRGIL C. SUMMER NUCLEAR STATION - NRC INTEGRATED INSPECTION
REPORT NO....
May 10, 2006
James M. Levine, Executive
Vice President, Generation
Mail Station 7602
Arizona Public Service Company
P.O. Box 52034
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR STATION - NRC PROBLEM IDENTIFICATION AND
RESOLUTION INSPECTION REPORT 05000528,529,530/2...
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
UNITED STATES NUCLEAR REGULATORY COMMISSION
BRIEFING ON NRC CORPORATE SUPPORT
+ + + + +
WEDNESDAY
April 15, 2009
+ + + + +
The Commission conv...
July 31, 2000
Gregory M. Rueger, Senior Vice President
and General Manager
Nuclear Power Generation Bus. Unit
Pacific Gas and Electric Company
Nuclear Power Generation, B32
77 Beale Street, 32nd Floor
P.O. Box 770000
San Francisco, California 94177
SUBJECT: DIABLO CANYON I...
Part IndexSec.Subpart A—General Provisions73.1 Purpose and scope.73.2 Definitions.73.3 Interpretations.73.4 Communications.73.5 Specific exemptions.73.6 Exemptions for certain quantities and kinds of special nuclear material.73.8 Information collection requirements: OMB ...
NUCLEAR REGULATORY COMMISSION
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
+ + + + +
BRIEFING ON
STATUS OF OCIO PROGRAMS,
PERFORMANCE AND PLANS
+ + + + +
Nuclear Regulatory Commission
One White Flint North
Rockville, Maryland
Wednesday,
January 30, 2002...
August 4, 2003
Mr. Fred R. Dacimo
Site Vice President
Entergy Nuclear Northeast
Indian Point Energy Center
295 Broadway, Suite 1
Post Office Box 249
Buchanan, NY 10511-0308
SUBJECT: INDIAN POINT 3 NUCLEAR POWER PLANT - NRC INTEGRATED
INSPECTION REPORT 05000286/2003006
Dea...