Lock-Up of Emergency Diesel Generator and Load Sequencer Control Circuits Preventing Restart of Tripped Emergency Diesel Generator
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
January 31, 1991
Information Notice No. 91-06: LOCK-UP OF EMERGENCY DIESEL GENERATOR
AND LOAD SEQUENCER CONTROL CIRCUITS
PREVENTING RESTART OF TRIPPED EMERGENCY
DIESEL GENERATOR
Addressees:
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose:
The information in this notice is intended to alert addressees of potential
problems involving the restart of a tripped emergency diesel generator (EDG)
because of "lock-up" of EDG or load sequencer control circuits. It is
expected that recipients will review the information for applicability to
their facilities and consider actions, as appropriate, to avoid similar
problems. However, suggestions contained in this information notice do not
constitute NRC requirements; therefore, no specific action or written
response is required.
Description of Circumstances:
On March 20, 1990, operations personnel at the Alvin W. Vogtle Plant, Unit
1, experienced difficulties when attempting to restart the in-service EDG.
In response to a valid bus undervoltage condition, the EDG had automatically
started and energized its associated 4.16 kV ac safety bus per design. The
EDG tripped after approximately one minute of operation. A spurious jacket
water high temperature signal is believed to have caused the trip. The load
sequencer had completed its cycle before the trip. The EDG could not be
restarted following the trip even though the condition that had caused the
trip had cleared and a valid undervoltage condition and automatic start
signal existed. The EDG control circuits had functioned as designed but had
locked-up such that subsequent restart attempts were prevented. Although
the EDG could have been started in the "emergency" mode by using the
emergency start switch at the local panel, the local and remote control
switches used for "normal" EDG start were ineffective. No equipment
failures or malfunctions were involved.
The design of the load sequencer circuits that provide an automatic start
signal upon sensing bus undervoltage and the interface between these
circuits and the interlocks in the EDG air start system are such that the
circuits will lock-up whenever a trip results in an undervoltage condition
on the associated
9101280052
.
IN 91-06
January 31, 1991
Page 2 of 3
safety bus. During the March 1990 event at the Vogtle Plant, the initial
attempts to reset the lock-up were unsuccessful, and the EDG was not
restarted for approximately 18 minutes. Had proper action been taken to
reset the locked-up circuits, the EDG could have been restarted promptly.
However, the operations personnel involved were not trained concerning the
lock-up condition, and procedures providing guidance concerning actions
required for restart did not exist. A detailed explanation of the design of
the Vogtle Unit 1 load sequencer and EDG air start system is presented in
NUREG 1410, "Loss of Vital AC Power and the Residual Heat Removal System
During Mid-Loop Operations at Vogtle Unit 1 on March 20, 1990."
On November 14, 1990, the 1A EDG at the Kewaunee Nuclear Power Plant was
being tested following replacement of the governor. Because of an improper
governor setting, the EDG tripped on overspeed before the load sequencer
completed its cycle. This trip caused the sequencer control circuits to
lock-up in a condition that would have prevented loading of the EDG
following a valid start. Maintenance technicians present during the testing
had to lift leads in the sequencer cabinet to clear the lock-up condition.
The first attempt to clear the lock-up condition was unsuccessful because
the leads were only removed momentarily, which resulted in remote
indications that led the operators to believe that the sequencer had been
reset. However, the leads were relanded before time delay relays could time
out and reset (approximately 90 seconds is required). Approximately two
hours were required for the plant personnel to troubleshoot the load
sequencer and complete successful testing of the EDG. Apparently, the plant
staff were not adequately trained to recognize and reset the lock-up
condition, and plant procedures were not appropriately detailed to allow
operators to cope with a situation where the EDG trips before the load
sequencer completes its cycle. The licensee is considering a modification
to the sequencer to install a conveniently located reset switch to allow
reset to be accomplished without having to lift leads.
Discussion:
These incidents have raised concerns regarding the understanding of EDG and
load sequencer control circuits and their interfaces, and the adequacy of
procedures for restarting EDGs following unexpected trips. EDG and load
sequencer control systems are often complex. As the result of either a
valid or spurious trip signal, an EDG can shut down at any time before,
during, or after cycling of the load sequencer. Successful mitigation of
the effects of accidents or transients and maintenance of the overall
reliability of EDGs depends upon operations personnel having (1) sufficient
knowledge of the associated instrumentation and controls; and (2) the
ability to recognize and reset a lock-up condition.
.
IN 91-06
January 31, 1991
Page 3 of 3
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate NRR project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contact: E. Nick Fields
(301) 492-1173
Attachment: List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Thursday, March 25, 2021