Information Notice No. 90-77: Supplement 1:Inadvertent Removal of Fuel Assemblies from the Reactor Core
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
February 4, 1991
Information Notice No. 90-77, SUPPLEMENT 1: INADVERTENT REMOVAL OF FUEL
ASSEMBLIES FROM THE REACTOR
CORE
Addressees:
All holders of operating licenses or construction permits for
pressurized-water reactors (PWRs).
Purpose:
This information notice supplement is intended to provide additional
information to that previously provided in Information Notice No. 90-77,
"Inadvertent Removal of Fuel Assemblies from the Reactor Core." It is
expected that recipients will review this information for applicability to
their facilities and consider actions, as appropriate, to avoid similar
problems. However, suggestions contained in this information notice do not
constitute NRC requirements; therefore, no specific action or written
response is required.
Description of Circumstances:
On October 4, 1990, at Indian Point Station Unit 3, while the upper core
internals package (UIP) was being lifted during preparations for defueling,
two fuel assemblies (FAs) were inadvertently lifted from the reactor core.
In response to this event, the NRC sent a Special Inspection Team to the
site to monitor the licensee's recovery of these FAs. The NRC issued
Information Notice No. 90-77 on December 12, 1990, to report this event.
The licensee's recovery activity was detailed in NRC Inspection Report
50-286/90-19, dated December 13, 1990.
The NRC also sent an Augmented Inspection Team (AIT) to the site after
recovery of the FAs to determine the probable cause and relevant facts of
this event and to evaluate the licensee's proposed corrective actions. The
AIT concluded that the two FAs were stuck to the UIP because of bent guide
pins on the upper core plate. The guide pins were bent during movement of
the UIP for reinstallation into the reactor vessel in May 1989. The
refueling crew had moved the UIP laterally before raising it to a height
above its storage stand adequate to avoid bumping the guide pins against the
stand. Refueling personnel did not recognize that the UIP had inadvertently
bumped against the storage stand and bent the guide pins. The UIP was thus
reinstalled with bent guide pins into the reactor vessel. As a result, the
bent guide pins severely damaged the top
9101290331
.
IN 90-77, Supplement 1
February 4, 1991
Page 2 of 3
nozzles of two FAs. In addition, the bent guide pins caused mechanical
deformation of a portion of the fuel rods in one of the two FAs. The
outwardly bent fuel rods in this FA caused mechanical deformation of the
fuel rods in an adjacent FA. None of these component-related damages were
identified by the licensee until the next refueling. The detailed
inspection findings are described in NRC Inspection Report 50-286/90-80,
dated January 8, 1991.
Discussion:
Since 1985, the NRC and the Institute of Nuclear Power Operations (INPO)
have provided the nuclear industry with three documents regarding the
inadvertent lifting of FAs from the reactor core. NRC Information Notice
86-58, "Dropped Fuel Assembly," and two INPO Significant Event Reports
(proprietary information) addressed events involving stuck FAs. As a result
of reviewing these generic communications, the licensee revised its
refueling procedure before this refueling outage to require the placement of
an underwater camera and extra lights on the reactor cavity floor to inspect
the UIP for stuck FAs. The procedure revision also included a step for
performing a video inspection after the upper internals were raised
approximately 1 foot above the reactor vessel flange. However, the
licensee's implementation of these procedural steps was not effective
because, as noted in the AIT findings, (1) the operators did not place extra
lights on the upper reactor cavity floor as directed by the note in the
procedure and (2) the operators did not move the camera around the reactor
vessel flange in order to view the underside of the upper internals from
different angles. At the time this step was performed, the lighting was
particularly inadequate at this location because about half of the lamps in
the reactor cavity were burned out, and the angle and distance of the lights
to the UIP created a dark shadow underneath the UIP. The problem of
ineffectiveness was compounded by the fact that the camera was in place only
on the eastern side of the vessel. Under these circumstances, the camera
apparently was not able to scan the distance across the vessel to detect the
stuck FAs, which were located peripherally on the western side of the
vessel. As a result, the stuck FAs were lifted upward and transported
horizontally for a short distance before being noticed by refueling
personnel.
The licensee utilized a refueling contractor (Westinghouse) to perform major
steps of the refueling operations. The licensee limited its overall
supervisory control of these operations because of the contractor's
extensive experience with the design of the plant and with refueling at
similar plants. This lack of oversight resulted in the licensee's failure
to provide adequate control, either supervisory or technical, over key steps
of the refueling operations. For example, the AIT found that the licensee's
refueling Senior Reactor Operator job tasks and responsibilities related to
maintaining overall supervision and coordination of the safety related
aspects of refueling operations were not identified or included in training.
The AIT also found the procedure that controlled movement of the UIP during
the previous refueling outage (May 1989) to be deficient in that (1) it did
not contain the detailed information necessary to inform refueling person-nel
on how to move the UIP without bumping it, (2) it contained action steps in
the form of notes, and (3) information important to the proper completion of
some procedural steps was included in notes located several pages away from
the steps.
.
IN 90-77, Supplement 1
February 4, 1991
Page 3 of 3
The AIT also identified an apparent shortcoming in the design of the storage
stand. The storage stand has three guide studs, which extend 3 feet 10
inches above the support stand flange seating surface (see Figure 1). These
guide studs provide guidance and protection for critical features of the UIP
during the lifting and setting-down evolutions involving the storage stand.
One of the most critical features of the UIP is the FA guide pins. The
guide pins are appended to the UIP upper core plate, which is located about
13 feet below the UIP upper support plate and lifting rig guide bushing.
Because of the short guide stud design (3 feet 10 inches), when the UIP is
being lowered onto the storage stand, the guide pins are approximately 8
feet below the stand flange by the time the lifting rig guide bushings
engage the stand guide studs. Similarly, when the UIP is being lifted from
the storage stand, at the point the lifting rig guide bushings clear the
stand guide studs, the guide pins, upper core plate, and some portion of the
upper internal guide tubes are still beneath the stand flange.
Consequently, the alignment of the stand guide studs and the UIP lifting rig
guide bushings is not a factor in preventing interference between the
storage stand flange and the guide pins.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
one of the technical contacts listed below or the appropriate NRR project
manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contacts: Peter C. Wen, NRR
(301) 492-0832
James A. Prell, RI
(215) 337-5108
Attachments:
1. Figure 1, Simplified Elevated View of West Side of Containment
2. List of Recently Issued NRC Information Notices
.ENDEND
Page Last Reviewed/Updated Tuesday, March 09, 2021