Information Notice No. 90-77: Inadvertent Removal of Fuel Assemblies from the Reactor Core
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
December 12, 1990
Information Notice No. 90-77: INADVERTENT REMOVAL OF FUEL ASSEMBLIES
FROM THE REACTOR CORE
Addressees:
All holders of operating licenses or construction y�tC��K�C�pressurized-water
reactors (PWRs).
Purpose:
This information notice is intended to alert addressees to potential
problems pertaining to the removal of nuclear fuel from the reactor core.
It is expected that recipients will review the information for
applicability to their facilities and consider actions, as appropriate,
to avoid similar problems. However, suggestions contained in this
information notice do not constitute NRC requirements; therefore, no
specific action or written response is required.
Description of Circumstances:
On October 4, 1990, Indian Point Nuclear Generating Unit 3 was in a
refueling outage. The licensee was removing the upper core support
structure (upper internals) from the reactor vessel in preparation for
refueling the core. Upon initiating a lateral move of the upper core
support structure, crane movement was stopped upon the discovery that two
peripheral fuel assemblies were attached to the bottom of the upper core
plate, which is part of the upper internals package. An underwater
camera inspection had been conducted after vertically lifting the upper
core support structure from the reactor vessel. This inspection was
prompted by earlier analysis of noise diagnostics data, confirming the
existence of a loose part which resembled a fuel assembly locating pin in
the steam generator channel head. Due to poor camera location and
lighting, the attached fuel assemblies were not recognized during the
initial camera inspection.
The licensee's fuel assembly retrieval procedure developed to facilitate
their recovery included: (1) performing a static lift (no lateral
movement) of the upper internals package until the fuel assemblies were
approximately 1 foot above the vessel flange, (2) rotating the upper
internals package so that the fuel assemblies would pass over the cavity
seal one at a time, and (3) positioning the assemblies such that they
could be lowered into specially fabricated steel baskets, which were
located in the deep end of the refueling cavity. During retrieval
activities, one of the assemblies inadvertently dropped into its basket
when the brakes on the overhead crane were applied with the assemblies
positioned over their baskets. The licensee lowered and
9012060205
.
IN 90-77
December 12, 1990
Page 2 of 3
freed the remaining assembly without incident. No radiological release
or breach of fuel integrity resulted from dropping the fuel assembly.
Discussion:
The licensee was using a 350,000 lb-capacity polar crane with a Dillon
load cell to lift the upper core internals package (weighing
approximately 119,800 lbs). The suspended fuel assemblies together
weighed approximately 2600 lbs. During the lift, the licensee did not
detect the additional weight because the weight of the upper internals
(with suspended fuel assemblies) was within the maximum allowable weight
of 125,800 lbs, as specified by the licensee's refueling procedure.
Each of the two assemblies were attached to the upper core plate by bent
fuel assembly guide pins as shown in Attachment 1. These guide pins
extend down-ward from the upper core plate and insert into two holes in
the upper nozzle of the fuel assembly when the upper core internals
structure is properly aligned over the top of the core. For each of the
suspended fuel assemblies, the licensee found that one guide pin was bent
and not inserted into the top nozzle hole (upper nozzle S-hole on
Attachment 1) of the fuel assembly, with the other guide pin bent and
wedged into the assembly. In this condition, the guide pin suspended the
assembly at an angle of approximately 7 degrees. The licensee has
determined that the fuel assembly guide pins were damaged during the
previous refueling outage when the upper internals package was being
removed from the upper internals storage stand.
Similar problems involving suspended fuel assemblies have occurred
previously. Information Notice 86-58, "Dropped Fuel Assembly," describes
a similar situation at the Haddam Neck Generating Station in which the
licensee inadvertently lifted an assembly when removing the upper
internals. In this situation, the assembly dropped 2 to 4 feet onto the
reactor core when the upper internals were moved laterally. The dropped
assembly and the two assemblies it impacted were damaged; however, no
radiological release occurred.
Another similar event occurred at the Palisades Nuclear Power Station (a
Combustion-Engineering plant) on September 3, 1988. At Palisades, the
licensee was removing the upper guide structure (UGS) from the vessel and
discovered a fuel bundle attached to the bottom. The licensee freed the
fuel bundle using a J-hook manipulated by a worker supported in a JIB
crane while the fuel bundle was suspended over the reactor core. The
root cause of the fuel bundle becoming attached to the UGS was attributed
to the bundle adhering to the UGS bundle guide pins.
Other licensees have identified fuel assembly guide pins that were bent
for a variety of reasons. At Byron Station, Unit 2, on October 8, 1990,
the licensee inadvertently bent approximately 8 guide pins due to an
error of a polar crane floor director. The crane floor director gave a
hand signal to lower the upper internals package prematurely, while
approximately 1/4 of the upper internals were still over the upper
internals storage stand. As a result, the upper internals package
impacted the storage stand and bent the guide pins.
.
IN 90-77
December 12, 1990
Page 3 of 3
Licensees may wish to consider reviewing their procedures and equipment
prior to performing activities which may lead to inadvertent damage to
fuel assembly guide pins and inspecting the guide pins before
reinstallation of the upper internals package into the reactor vessel.
When reviewing their procedures (to assure the ability of the reactor
cavity seal to withstand the mechanical, thermal, and radiation impacts
from a dropped fuel assembly) licensees may also wish to consider the
need to carefully inspect the upper core support structure as it is
initially raised from the reactor vessel to ensure that no core
components are suspended.
This information notice requires no specific action or written response.
If you have any questions about the information in this notice, please
contact the technical contact listed below or the appropriate NRR project
manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contact: John Thompson, NRR
(301) 492-1171
Attachments:
1. Indian Point 3 Detailed View Showing Suspended
Fuel Assembly from Bottom of Upper Internals
Package
2. List of Recently Issued NRC Information Notices
.ENDEND
Page Last Reviewed/Updated Wednesday, March 24, 2021