Information Notice No. 85-66: Discrepancies Between As-built Construction Drawings and Equipment Installations
SSINS No.: 6835
IN 85-66
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
August 7, 1985
Information Notice No. 85-66: DISCREPANCIES BETWEEN AS-BUILT
CONSTRUCTION DRAWINGS AND EQUIPMENT
INSTALLATIONS
Addressees:
All nuclear power reactor facilities holding an operating license (OL) or a
construction permit (CP).
Purpose:
This information notice is to alert recipients of a potentially significant
generic problem regarding as-built construction drawings not correctly or
completely reflecting equipment installations. Modifications of existing
installations also may be susceptible to the problems discussed in this
information notice. It is expected that recipients will review the
information for applicability to their facilities and consider actions, if
appropriate, to preclude a similar problem occurring at their facilities.
However, suggestions contained in this information notice do not constitute
NRC requirements; therefore, no specific action or written response is
required.
Description of Circumstances:
Fermi Unit 2
During routine NRC prelicensing inspections of as-built design and
construction drawings and specifications at Fermi Nuclear Power Plant Unit
2, from April 1984 to October 1984 several discrepancies in the electrical
and instrumentation and control (I&C) installations were discovered, which
construction and preoperational testing had not identified.
In response to the NRC findings at Fermi, the licensee conducted an
approximately 100 percent reinspection of electrical and I&C installations.
That inspection effort resulted in the identification of over 7300
discrepancies and errors between as-built field configurations and
associated design and construction drawings and specifications. There were
154 discrepancies which, if left uncorrected, could result in the loss or
incorrect function of a safety-related component or system. Examples of
these discrepancies were wiring errors, unidentified jumpers, wrong tubing
connections, and wrong installed components. There were 300 discrepancies
that had correct design documents but incorrect installations that could
impair safe operations.
8508050449
.
IN 85-66
August 7, 1985
Page 2 of 3
Examples of these discrepancies were ungrounded cable shields, missing
hardware, and wrong nameplates. There were 1900 discrepancies which had
correct as-built hardware but deficient drawings. Examples of these
discrepancies included wiring installed that was not shown on the applicable
drawing, wiring details that differed from the installation drawing, and
incorrect cable numbers on the drawings. There were 5000 additional minor
discrepancies which would not have impacted or impaired safe plant
operations directly such as incorrect wire tags, equipment layouts that did
not match the drawings, and inconsistencies in wire tagging methods.
Extensive actions by the applicant were necessary to correct the most
significant discrepancies before an operating license was issued by the NRC.
Rancho Seco
A reactor coolant system high point vent line addition was made at Rancho
Seco during the 1983 refueling outage as part of the TMI required
modifications. Part of the modification included adding cross bracing and
revising supports for the adjacent nitrogen supply line. Although records
indicate this work had been done and inspected it had actually not been
performed. In addition, a removable piping spool piece used to isolate the
nitrogen supply was not replaced by a rigid piece as required. The resulting
unsupported 4 foot length of 1 inch diameter pipe caused a fatigue failure
at a high point vent weld resulting in a 20 gallon per minute non-isolatable
primary coolant leak. This event is similar to previous discrepancies
identified between the as-built and as-designed piping systems at a number
of nuclear power plants that led to issuance of IE Bulletin 79-14, "Seismic
Analyses for As-Built Safety-Related Piping Systems." Resolution of the
actions requested by that bulletin has resulted in extensive reanalysis
and/or modifications of piping systems in many nuclear power plants.
Construction Appraisal Team Inspections A number of problems with
construction activities which may lead to discrepancies between equipment
installations and as-built drawings were identified by NRC Construction
Appraisal Team (CAT) inspections at 10 facilities from September 1982 to
January 1985.
Discussion:
To assure that an adequate level of safety exists or will exist at all
nuclear power plants, it is required that all safety related as-built design
and construction drawings match the plant hardware. Requirements and
measures to control documents are identified in 10 CFR 50, Appendix B;
NUREG-0800, Standard Review Plan, Rev. 2 of Section 17.1; ANSI N45.2-1977,
Section 7; and ANSI N.8.7-1976, Section 5.2.15, as applicable.
.
IN 85-66
August 7, 1985
Page 3 of 3
No specific action or written response is required by this information
notice. If you have any questions about this matter, please contact the
Regional Administrator of the appropriate regional office or this office.
Edward L. Jordan Director
Division of Emergency Preparedness
and Engineering Response
Office of Inspection and Enforcement
Technical Contact: James C. Stewart, IE
(301) 492-9061
Attachments:
1. Discrepancies Identified During Construction
Appraisal Team Inspections
2. List of Recently Issued IE Information Notices
.
Attachment 1
IN 85-66
August 7, 1985
Page 1 of 1
Discrepancies Identified During
Construction Appraisal Team Inspections
During the Braidwood CAT inspection the NRC team noted a failure to annotate
unincorporated design changes on controlled design documents. The most
significant finding in this area was design change documents written against
superseded revisions of the approved drawings; this resulted in a pipe
support being installed and inspected to other than the latest approved
design.
Programmatic concerns were noted by the NRC team in two areas during the
Shearon Harris CAT inspection: (1) lack of verification of piping and pipe
support/restraint location to original design requirements and (2) lack of
an ongoing program to effectively identify and resolve hardware clearance
problems early in the construction process. Both of these concerns involve
practices that could result in extensive inspection, analyses, and rework
efforts very late in the construction schedule.
The River Bend CAT inspection noted that numerous cable tray supports did
not meet the drawing configurations that were utilized for determining
support loading. The applicant failed to consider the generic implications
of identified deficiencies. Improper or inadequate fastener locking was
identified, including unbent or missing cotter pins, no staking of threads,
loose or missing locknuts, and inadequate lock wiring. These deficiencies
indicated both inadequate field quality control (FQC) inspection and
alteration of completed and accepted work by construction personnel.
The Nine Mile Point 2 CAT inspection identified problems in the document
control program that indicated the crafts and inspectors may not have been
using the latest design documents in the performance of their work.
Inspection reports often did not reflect the drawing revision to which the
installation was inspected. Adding to the document control problem was the
high rate of design change initiation and the inability to maintain and
revise construction drawings in a timely manner to reflect such changes. The
NRC CAT inspectors identified that over 30 percent of all design change
documents resulted from errors or inadequate information provided on
previously issued changes. Furthermore, rather than taking measures to
identify the reasons for the high change notice generation rate, a
procedural requirement for incorporation of changes in drawings had simply
been circumvented by the licensee to allow construction to continue without
timely design change update.
The results of the Comanche Peak CAT inspection indicated a breakdown in
fabrication, installation, and inspection in the HVAC area. The licensee's
quality assurance program had not ensured that certain hanger, support,
electrical and mechanical equipment was installed to the latest design
documents, and commensurately that the appropriate inspection was conducted
to the latest design documents.
Page Last Reviewed/Updated Tuesday, March 09, 2021