Information Notice No. 84-79: Failure to Properly Install Steam Separator at Vermont Yankee
SSINS No.: 6835
IN 84-79
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
November 5, 1984
Information Notice No. 84-79: FAILURE TO PROPERLY INSTALL STEAM
SEPARATOR AT VERMONT YANKEE
Addressees:
All boiling water reactor (BWR) facilities holding an operating license (OL)
or a construction permit (CP).
Purpose:
This information notice is being provided as a notification of a potentially
significant problem pertaining to the failure to properly install the steam
separator while reassembling the reactor internals following a refueling and
maintenance outage. It is expected that recipients will review this notice
for applicability to their facilities and consider actions, if appropriate,
to preclude a similar problem from occurring at their facilities. However,
suggestions contained in this notice do not constitute NRC requirements;
therefore, no specific action or written response is required.
Description of Circumstances:
On September 11, 1984, having withdrawn control rods to the 100% power
pattern, Vermont Yankee proceeded to increase power from 88% by increasing
recirculation flow. In the 94-96% power range, the increase in recirculation
flow did not result in the expected increase in power. Instead, the
power-to-flow relationship departed from a linear relationship in a step
decrease in this range and resumed linearity above it. Also, the temperature
in the annulus area was 2 to 3 degrees hotter than normal. On September 16,
1984, the licensee notified the NRC that licensee personnel were
investigating the possibility that the steam separator (also called shroud
head) lifted during high core flow. The plant A was shut down on September
18, 1984, to determine the condition of the separator.
The holddown bolts were inspected using an underwater TV camera and found to
be oriented properly, but not tightened. Gaps from 1/4 to 5/8 inch existed
between the tee-bar and the clips on the shroud (see Figure 1). The steam
separator was removed and the shroud flange was examined for damage. No
damage was found. Internals were reassembled using procedures that emphasize
steps necessary to verify proper installation of the steam separator and
dryer.
8411010487
.
IN 84-79
November 5, 1984
Page 2 of 2
The steam separator is installed by placing it in position on the shroud. A
special tool, (see Figure 2) is used to turn the locator handle to orient
the tee-bars tangent to the shroud. The tee-bars are then snugged up to the
clips on the shroud by depressing the keeper nut and turning the wrench
handle to rotate the tensioning nut. In the case of Vermont Yankee, the
second operation was begun but not completed, leaving the gaps that were
observed. The possibility exists that extensive operation at high enough
power to cause the separator to lift would cause damage to the mating
surfaces of the shroud and steam separator by battering or steam erosion;
however, this was not observed at Vermont Yankee. If damage had occurred to
the mating surfaces such that repair was necessary to prevent escalation of
the damage, such repairs would require an extended outage and would likely
result in large exposures to the maintenance work force. This would be
inconsistent with ALARA principles.
No specific action or written response is required by this information
notice. If you have any questions regarding this matter, please contact the
Regional Administrator of the appropriate NRC regional office or this
office.
Edward L. Jordan, Director
Division of Emergency Preparedness
and Engineering Response
Office of Inspection and Enforcement
Technical Contact: Mary S. Wegner, IE
(301)492-4511
Attachments:
1. Figure 1, Steam Separator, and Figure 2, Steam Separator Bolt Wrench
2. List of Recently Issued IE Information Notices
Page Last Reviewed/Updated Tuesday, March 09, 2021