Bulletin 77-07: Containment Electrical Penetration Assemblies at Nuclear Power Plants under Construction
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D. C. 20555
December 19, 1977
IE Bulletin No. 77-07
Page 1 of 3
CONTAINMENT ELECTRICAL PENETRATION ASSEMBLIES AT NUCLEAR POWER PLANTS
UNDER CONSTRUCTION
Description of Circumstances:
On October 3, 1977, Northeast Nuclear Energy Company reported to the NRC
Region I Office that two control valves installed inside containment at
Millstone Unit No. 2 demonstrated abnormal operational characteristics.
The licensee reported that an unexpected closure of a letdown flow stop
valve occurred. While investigating this problem the normally closed
safety injection recirculation return line drain valve was found to be
in the open position. Investigation of these events revealed the cause
for failure to be electrical shorts between conductors within a
containment low voltage penetration assembly.
The licensee subsequently determined that the wiring for both of the
valves shared the same low voltage module in an electrical penetration.
Electrical tests by the licensee revealed that 15 of the 85 conductors
in the suspect connector module exhibited decreased insulation resistance
between conductors. Based on this finding it is believed that an
electrical path between adjacent circuits in the connector module was
established. This resulted in spurious operation of the valves. Similar
resistance checks performed on the remaining low voltage modules within
the affected penetration assembly revealed 17 additional conductors with
reduced insulation resistances. All conductors with resistances less than
20 megohms were disconnected and their circuits were reconnected through
spare conductors.
Examination of the three remaining low voltage penetration assemblies
identified 7 additional conductors with resistances of less than 20
megohms. Each of these circuits was also reconnected through a spare
conductor.
Investigation showed that the reduced insulation resistance was probably
caused by moisture accumulation within the penetration assembly together
with small fissures in the epoxy seals surrounding each conductor in the
module. The licensee believes that moisture penetrating these cracks
reduced the insulation resistance between adjacent
.
IE Bulletin No. 77-07
December 19, 1977
Page 2 of 3
conductor. To prevent further degradation from moisture buildup within the
penetration assemblies, the licensee re-established a dry nitrogen
pressure of 24 psig in the penetrations.
Subsequently, the licensee reported that a second event of a similar
nature occurred on October 14, 1977. In this instance, the sample
isolation valve for the pressurizer surge line failed to close on
command. Investigation into this event indicated that electrical shorts
between conductors due to a moisture accumulation problem were the
probable cause for valve misoperation. The shorted wires were
disconnected and the valve was de-energized in the closed position.
In discussions on the issue with the licensee and the electrical
penetration vendor, General Electric Company, NRC staff determined that
maintenance of nitrogen pressure is essential to the integrity of both
high and low voltage penetration assemblies. The General Electric Company
specifies in its penetration assembly maintenance and operation manual
that a 15 psig dry nitrogen pressure should be maintained on low voltage
units while 30 psig should be maintained on high voltage units.
Action To Be Taken By Applicants Of All Power Reactor Facilities With a
Construction Permit:
Containment Electrical Penetrations - For safety related systems
1.0 Do you have containment electrical penetrations that are of the
G. E. Series 100, or are otherwise similar in that they depend upon an
epoxy sealant and a dry nitrogen pressure environment to ensure that the
electrical and pressure characteristics are maintained so as to ensure
the functional capability as required by the plant's safety analysis
report; namely, (l) to ensure adequate functioning of electrical safety-
related equipment and (2) to ensure containment leak tightness? If you
do use penetrations of this type at your facility describe the
manufacturer and model number of these units.
1.1 If you do not have penetration assemblies of the type(s) referenced
in Item 1.0 above, describe the type(s) of penetrations, e.g.,
manufacturer and model number now in use or planned for use in safety
systems at your facility.
.
IE Bulletin No. 77-07
December 19, 1977
Page 3 of 3
1.2 Do the transition connector pins imbedded in the epoxy as discussed
in Item 1.0 above, have an insulation jacket?
2.0 For those penetrations referenced in Item 1 above, has the
manufacturer's prescribed nitrogen pressure been maintained at all times
during shipping, storage and installation?
3.0 Is there a need, as determined by either the vendor or yourself, to
maintain penetrations pressurized during normal operation, to assure
functionability during a LOCA.
3.1 What measures have you taken to ensure that penetrations of this type
will perform their design function under LOCA conditions? (design
reviews, analyses or tests)?
3.2 Are the measures that provide this assurance adequate to satisfy the
Commission's regulations (GDC 4, Appendix A to Part 50; QA Criteria,
Appendix B to Part 50)?
4.0 Provide your response to Items 1.0 through 3.2 above in writing
within 30 days. Responses should be submitted to the Director of the
appropriate NRC Regional Office. A copy of your response should be
forwarded to the U. S. Nuclear Regulatory Commission, Office of
Inspection and Enforcement, Division of Reactor Construction Inspection,
Washington, D. C. 20555.
Approved by GAO, B180225 (R0072); clearance expires 7-31-80. Approval was
given under a blanket clearance specifically for identified generic
problems.
Page Last Reviewed/Updated Tuesday, March 09, 2021