0350 Oversight Panel for 2004
The Nuclear Regulatory Commission staff has established a special oversight panel to coordinate the agency's activities in assessing the performance problems associated with the corrosion damage to the reactor vessel head at the Davis-Besse Nuclear Power Plant, monitoring corrective actions, and evaluating the readiness of the plant to resume operations.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date |
Description |
12/06/04 |
Category 1 Meeting: Davis-Besse 0350 Panel Public Meeting
|
09/28/04 |
Category 1 meeting: To discuss licensee performance and planned activities as part of the IMC 0350.
|
07/13/04 |
Category 1 Meeting: Discuss licensee performance an dplanned activities as part of the IMC 0350 process at Davis-Besse.
|
05/13/04 |
Category 1 Meeting: Discuss plant performance and the NRC's activities related to the IMC 0350 process at Davis Besse.
|
04/08/04 |
Category 1 Meeting: Discuss licensee performance and planned activities as part of the IMC 0350 Process
|
04/08/04 |
Category 3 Meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station
|
02/12/04 |
Category 1 Meeting: Allow the licensee to state the basis for their request to restart reactor operations at the Davis-Besse Nuclear Power Station. The NRC will not be providing a response to the restart request at this meeting.
|
02/12/04 |
Category 1 Meeting: Discuss the results of the Follow-up Restart Readiness Assessment Team Inspection and the Follow-up Management and Human Performance Team Inspection
|
01/21/04
RESCHEDULED FROM 1/13/04
|
Category 1 Meeting: Discuss licensee performance and progress on the Return to Service Plan as part of the IMC 0350 Process.
|
For related information see Reactor Pressure Boundary Integrity Issues for Pressurized Water Reactors.