cROP Historical Performance from Previous Quarters

Below are links to historical snapshots of plant performance from previous quarters as displayed on the web since the inception of the Construction Reactor Oversight Process.

On July 31, 2017, South Carolina Electric & Gas Company (SCE&G) announced that it had stopped construction of V.C. Summer Units 2 and 3, as documented in a letter dated August 17, 2017.

The NRC ceased inspection and Construction Reactor Oversight Process activities for V.C. Summer Units 2 and 3 after the July 31 announcement. This page contains information related to V.C. Summer Units 2 and 3 inspection and Construction Reactor Oversight Process activities completed prior to July 31, 2017.

On August 3, 2022, the NRC made the finding that the acceptance criteria in the combined license for Vogtle Electric Generating Plant, Unit 3 was met in accordance with Section 185b. of the Atomic Energy Act of 1954, as amended, and Title 10 of the Code of Federal Regulations, Section 52.103(g), as found here.  This finding effectively transitioned Vogtle Unit 3 from the Construction Reactor Oversight Process to the Reactor Oversight Program. This page contains information related to Vogtle Unit 3 inspection and Construction Reactor Oversight Process activities completed prior to June 30, 2022.

Construction Action Matrix Summaries

2010Q3 | 2010Q4 | 2011Q1 | 2011Q2 | 2011Q3 | 2011Q4 | 2012Q1 | 2012Q2 | 2012Q3 | 2012Q4 | 2013Q1 | 2013Q2 | 2013Q3 | 2013Q4 | 2014Q1 | 2014Q2 | 2014Q3 | 2014Q4 | 2015Q1 | 2015Q2 | 2015Q3 | 2015Q4 | 2016Q1 | 2016Q2 | 2016Q3 | 2016Q4 | 2017Q1 | 2017Q2 | 2017Q3 | 2017Q4 | 2018Q1 | 2018Q2 | 2018Q3 | 2018Q4 | 2019Q1 | 2019Q2 | 2019Q3 | 2019Q4 | 2020Q12020Q2 | 2020Q3 | 2020Q4 | 2021Q1 | 2021Q2 | 2021Q3 | 2021Q4 | 2022Q1 | 2022Q2 | 2023Q3 | 2022Q4

Cross Cutting Issues Summary

2010Q4 | 2011Q2 | 2011Q4 | 2012Q2 | 2012Q4 | 2013Q2 | 2013Q4 | 2014Q2 | 2014Q4 | 2015Q2 | 2015Q4 | 2016Q2 | 2016Q4 | 2017Q2 | 2017Q4 | 2018Q2 | 2018Q4 | 2019Q2 | 2019Q4 | 2020Q22020Q4 | 2021Q2 | 2021Q4 | 2022Q2 | 2022Q4

Individual Plant Performance Summaries

V.C. Summer Unit 2:
2012Q1 | 2012Q2 | 2012Q3 | 2012Q4 | 2013Q1 | 2013Q2 | 2013Q3 | 2013Q4 | 2014Q1 | 2014Q2 | 2014Q3 | 2014Q4 | 2015Q1 | 2015Q2 | 2015Q3 | 2015Q4 | 2016Q1 | 2016Q2 | 2016Q3 | 2016Q4 | 2017Q1 | 2017Q2 | 2017Q3 |

V.C. Summer Unit 3:
2012Q1 | 2012Q2 | 2012Q3 | 2012Q4 | 2013Q1 | 2013Q2 | 2013Q3 | 2013Q4 | 2014Q1 | 2014Q2 | 2014Q3 | 2014Q4 | 2015Q1 | 2015Q2 | 2015Q3 | 2015Q4 | 2016Q1 | 2016Q2 | 2016Q3 | 2016Q4 | 2017Q1 | 2017Q2 | 2017Q3 |

Vogtle Unit 3:
2012Q1 | 2012Q2 | 2012Q3 | 2012Q4 | 2013Q1 | 2013Q2 | 2013Q3 | 2013Q4 | 2014Q1 | 2014Q2 | 2014Q3 | 2014Q4 | 2015Q1 | 2015Q2 | 2015Q3 | 2015Q4 | 2016Q1 | 2016Q2 | 2016Q3 | 2016Q4 | 2017Q1 | 2017Q2 | 2017Q3 | 2017Q4 | 2018Q1 | 2018Q2 | 2018Q3 | 2018Q4 | 2019Q1 | 2019Q2 | 2019Q3 | 2019Q4 | 2020Q1 | 2020Q2 | 2020Q32020Q4 | 2021Q12021Q2 | 2021Q3 | 2021Q4 | 2022Q1 | 2022Q2

Vogtle Unit 4:
2012Q1 | 2012Q2 | 2012Q3 | 2012Q4 | 2013Q1 | 2013Q2 | 2013Q3 | 2013Q4 | 2014Q1 | 2014Q2 | 2014Q3 | 2014Q4 | 2015Q1 | 2015Q2 | 2015Q3 | 2015Q4 | 2016Q1 | 2016Q2 | 2016Q3 | 2016Q4 | 2017Q1 | 2017Q2 | 2017Q3 | 2017Q4 | 2018Q1 | 2018Q2 | 2018Q3 | 2018Q4 | 2019Q1 | 2019Q2 | 2019Q3 | 2019Q4 | 2020Q1 | 2020Q2 | 2020Q3 | 2020Q4 | 2021Q12021Q2 | 2021Q3 | 2021Q4 | 2022Q1 | 2022Q2 | 2022Q3 | 2022Q4

Page Last Reviewed/Updated Thursday, June 15, 2023